What are my lien rights with respect to a change order?

CaliforniaChange OrdersMechanics Lien
Anonymous Contractor

What are my lien rights with respect to a change order that my client refuses to approve? Do I have to bill them for the disputed amount? Can then lien amount only be for the contracted amount or can I include the change order as well?

1 reply

Good morning, It really depends on your individual situation, but generally, it makes sense to bill for the disputed change order.  The billing for the disputed change order becomes part of your "contract amount" and your lien should generally include the amount of the change order.  You may want to consult a construction attorney to verify this course of action for your specific situation, however, to be sure.
NOTE: The information presented here is general in nature and is not intended nor should be construed as legal advice for any particular case or client. The
content contained herein is published online for informational purposes only, may not reflect the most current legal developments, verdicts or settSee More...