Material not being released from sub contractor warehouse

New YorkBack Charges

Hello, I am a sub coantractor. I sub contractoed another sub to deliver and install office furniture project. The balance due to the other sub is $73k. There were and are so many issues being their negligiance that I offered $40k. They are holding product that has been shipped to their warehouse by my clients. My client did not change address were product was to be dleivered and now the other sub contractor will not releae the product to me with me paying him $50k. I offered $40k and they said no. Do I have a stance to get the other product out of their warehosue? Thnk you

1 reply

Feb 15, 2021
This is a difficult problem. The sub holding the material has a significant bargaining position. pay the $50K get the material and then have your arguments. it is the only cost effective way to get your job completed.