how can i find what the cost over runs for each individual bridge are for the pa rapid bridge project?

4 weeks ago

i’m looking to find out if there were additional extra charges from Plen Walsh to the state of PA

Senior Legal Associate Levelset
109 reviews

It looks like there have been some time extensions and cost overruns to the Rapid Bridge Replacement Project, which are well documented in these articles from back in 2017 and 2018: 3-Year project to replace 558 small bridges extended by four months (2017); and PennDot’s speedy bridge project lags (2018). However, unfortunately, I’m not quite sure where to find the overruns incurred for individual bridges.

It might also be helpful to request that information directly from the Pennsylvania Department of Transportation, which you can do here under Pennsylvania’s Right to Know Laws.