Filing a Lien

California
Jo Gessert
President at Jack's Equipment Rental Inc. DBA Jack's Construction Company

Can a lien be filed if a preliminary lien was not filed?

2 replies

Levelset Admin at Levelset
| 335 reviews
Oct 20, 2021

Filing a preliminary notice isn't necessarily required, but serving a preliminary notice is typically a prerequisite to filing a mechanics lien in California.  

Generally, all parties who didn't contract directly with the property owner are required to send a 20-day Preliminary Notice in order to secure lien rights in California. However, if the project has a lender, then direct contractors (such as GCs) are required to send notice to the lender. Late notice is still effective, but will only secure lien rights for the value of labor and/or materials provided in the 20 days preceding the notice and everything thereafter. 

Here are some resources you may find helpful:

NOTE. The information presented here is for informational purposes only. It is not legal advice and should not be construed nor relied upon as such.
Furthermore, this posting does not create an attorney-client relationship. If you need legal advice, seek the counsel of a licensed, local attorney.See More...