Does prelim 20 day notices include weekends as well. If so, does the first day start from the day the job started or ended?

1 reply

Partner at Flores Ryan, LLP
| 280 reviews
Jan 19, 2020
Yes, the 20 days includes weekends. The notice must be sent within 20 days of first furnishing labor and/or materials (day the job started).
Do not act on the information contained herein without seeking the advice of licensed counsel. The information presented here is general in nature and is not