Menu
Home>Levelset Community>Legal Help>Can I file a Lien for work completed if the scope changed once I started?

Can I file a Lien for work completed if the scope changed once I started?

CaliforniaPreliminary Notice
Anonymous Material Supplier

I supplied staging (all furniture items) to a property to be listed for sale. An estimate was provided and a contract based on the estimate. After completing the work and adding furniture pieces that were initially credited on the estimate (I was told the items were on site and they were not) I added items necessary to complete the job. The house sold and now the owner does not want to pay me for the added materials. Do I have any recourse? The project began May 1st and ended June 11th.