Menu
Home>Levelset Community>Legal Help>Can I as a contractor back out of a contract if the job is more then 3/4 way done and still get paid. For work done

Can I as a contractor back out of a contract if the job is more then 3/4 way done and still get paid. For work done

New YorkChange Orders

We are building a garage and the customers are being unruly the husband wants things done one the wife wants it another then they will yell at us because they both want it done different ways works already have walked off the job

3 replies

Aug 25, 2022

If you want to simply walk of the job, you could subject yourself to a breach of contract claim, you must cover yourself in writing first. If there is a written contract, you must follow the procedures set forth therein, it's possible to still get paid, but not such a simple answer. Speak to a construction lawyer, this one should be simple, but more information is needed. 

0 people found this helpful
Helpful
Aug 26, 2022

I really appreciate you giving this useful information. In the near future, I want to read more of your posts <a href="https://findaword.co/5-letter-words">5 letter words</a>.

0
Report Spam
Aug 26, 2022

I really appreciate you giving this useful information. In the near future, I want to read more of your posts 5 letter words 

0
Report Spam