Menu
Home>Levelset Community>Legal Help>Am I able to file a mechanics lien if the last day of labor was on 11/16/17 but I have not invoiced for the retention?

Am I able to file a mechanics lien if the last day of labor was on 11/16/17 but I have not invoiced for the retention?

CaliforniaLien DeadlinesMechanics Lien
Anonymous Contractor

I have completed all billings except for the retention billing. They are now past due on billing I submitted on 11/16/17 and would like to place a mechanics lien on the property. I am not sure if the retention billing not being completed will mess that up.

1 reply

Levelset Admin at Levelset
| 1,003 reviews
Feb 21, 2018
That's a good question - the timelines can be confusing when it comes to mechanics lien deadlines. In California, the deadline to file a mechanics lien will actually not be based on the retention billing. Instead, it will have more to do with project role and when work was completed (or ceased) or whether a Notice of Completion or Cessation was filed. A direct contractor must record his Claim of Lien after completion of the direct contract, and before the earlier of either 90 days after completion of the work of improvement; or 60 days after the owner records a Notice of Completion or Cessation. A claimant other than a direct contractor must record his mechanics lien after the claimant ceases to provide work, and before the earlier of either: 90 days after completion of the work of improvement; or, 30 days after the owner records a Notice of Completion or Cessation.
The information presented here is not legal advice and should not be construed as such. Rather, this content is provided for informational purposes. Do not
act on this information as if it is advice. Further, this post does not create any attorney-client relationship. If you do need legal advice, seek the helSee More...
See More...
0 people found this helpful
Helpful