About South Dakota Final Conditional Lien Waiver Form

This sd final conditional waiver (also called a final conditional lien release) should be used when the final payment for a project is expected but has yet to be received on a project in the state of sd. Signing this waiver signifies that no further payments are expected following the payment described in the waiver.

This sd lien waiver form is “conditional” on the receipt of the payment and will be invalid if payment is not received. Because of this condition, it’s ok to use if payment has not yet been received.

Pro tip: If payment has already been received in full, an “unconditional” waiver may be more appropriate.

Complete the form on the right to download your Free South Dakota Final Conditional Lien Waiver Form template that can be filled out with a PDF editor or by hand after printing. Use this template to easily send a final conditional lien release in a construction project in sd.

South Dakota Final Conditional Lien Waiver Form

Skip the hassle of sending a South Dakota Lien Waivers yourself.

We’re the Lien Waivers experts. With us it’s fast, easy, affordable, and done right!
mechanics lien county recorder e-filing.

South Dakota County Recorders

Looking to file/record a mechanics lien in South Dakota? You'll need to get your South Dakota mechanics lien filed and recorded with the county recorder in the county where the construction project is located. Here is a listing of all county recorders in South Dakota. Click on any county to find more information about how to get your lien recorded in that county.

Brookings
Brookings County Register of Deeds
520 3rd St Suite 120
Brookings, South Dakota, 57006
phone: (605) 696-8240
fax:

Brown
BROWN COUNTY REGISTER OF DEEDS
25 MARKET ST
ABERDEEN, South Dakota, 57401
phone: (605) 626-7140
fax:

Codington
Codington County Register of Deeds
14 1st Ave. SE
Watertown, South Dakota, 57201
phone: (605) 882-6278
fax:

Davison
Register of Deeds
200 East 4th Ave.
Mitchell, South Dakota, 57301
phone: (605) 995-8616
fax:

Grant
Grant County Register of Deeds
210 E 5th Ave
Milbank, South Dakota, 57252
phone: (605) 432-4752
fax:

Lawrence
Register of Deeds
90 Sherman St
Deadwood, South Dakota, 57732
phone: (605)-578-3930
fax:

Minnehaha
Register of Deeds
415 N. Dakota Ave.
Sioux Falls, South Dakota, 57104
phone: (605) 367-4223
fax:

Pennington
Pennington County Register of Deeds
130 Kansas City St
Rapid City, South Dakota, 57701
phone: 605-394-2177
fax:

Turner
Turner County Register of Deeds
400 S Main
Parker, South Dakota, 57053
phone: (605) 297-3443
fax:

Walworth
Register of Deeds
4304 4th Avenue
Selby, South Dakota, 57472
phone: (605) 649-7057
fax:

Yankton
Yankton County Register of Deeds
321 W. Third St., Suite 205
Yankton, South Dakota, 57078
phone: (605) 260-4400, Ext 5
fax:

FAQs about South Dakota Final Conditional Lien Waiver Form

Recent Questions & Answers About South Dakota Lien Waivers
Receipts and Lien Waivers

I live in Missouri and am selling my condo. I completed minor upgrades (painting, fixtures, new stove and frig). My Title company is requesting receipts...

Do we need to provide property owner the subcontractor lien waivers?

We are a general contractor and the client asked for lien waivers from us along with the subcontractors. We usually mark up the subcontractors' costs,...

Can I file a lien against someone’s house?

I was contracted for a large scale multi-destination move for $15,000. The contract was agreed to and signed on 10 February to be completed by...

submit a waiver to release lien on my property

I'm an owner and have I have a waiver from my contractor that I'd like to submit to release lien on my property

Does this mean the general contractor can come back on us?

We received a partial lien waiver and there is a paragraph in the lien waiver I have never seen before. It says the following: (This...

Waiver of Lien

I have a Lien Waiver that releases my rights. However, on the ROL it is marked as an Interim and not a final Waiver. The...

Ask an Expert for Free