We worked this job until they stopped paying. Then we left the site and removed our tools. Last month they were claiming that they were going to pay and wanted to get our payments corrected. After supplying all required information they quite talking to us so we filed a lien. Our suppliers also filed...Read More...Read More
I'm a General Contractor on an exterior painting project for a Condo HOA. The agreement/contract was signed by the president of the HOA for the work. All owners have paid their respective balances except for one owner. Do I lien the specific owner unit, or the entire building? This notice of right to li...Read More...Read More
I sent a Prelim lien on a job. They didn't pay us a dime and went out of business (public job). I filed a lien on the GC bond. The bond company asked for a copy of the Preliminary. I went on to only find out the pre-lim went to a different contractor than what was on the lien. Am I out $20K because researc...Read More...Read More
I hired a contractor to paved my front and backyard. The project was completed in September. I paid the contractor I full. In November I received a notice intent of lien on my property from the supplier because the contractor didn't pay them. I called the contractor and he told me he would take car...Read More...Read More
I was hired to do some concrete work and the owner wasn't satisfied with it and then the builder came at me and said that there was an issue with concrete work, so we came to an agreement that I was going to pay for the demo to take it down I was going to pay for the demo at my cost and once th...Read More...Read More
Our company has separate divisions for water mitigation and reconstruction. We have a shared client that we need to lien for both the reconstruction invoice, as well as the water invoice. Can those both be on the same lien?...Read More
I was hired to do some concrete work and the owner wasn't satisfied with it and then the builder came at me and said that there was an issue with concrete work, so we came to an agreement that I was going to pay for the demo to take it down I was going to pay for the demo at my cost and once th...Read More...Read More
A contractor cancels bond insurance and buys one from a different company in the middle of the job. Which company can I file with? Does the canceled bond have any obligation to payout for work done during the effective period once the bond is cancelled? Is there any protection for honoring the warr...Read More...Read More
A job was delivered almost 90 days ago. We are a cabinet manufacturer and also do site measure and fixes. Last week we came tom the job site to flip a cabinet panel, and sand down a shelf, and today the owner stopped by again and sanded rest of the shelves on site , and we also made a deliver...Read More...Read More
A preliminary notice wasn't done for a project in Washington. We are near the end of the job and there's some issues arising. I understand we can send a 60 day notice late and that will still keep our rights for costs 60 days prior to the notice but, my main concern is protecting our lien rights on the rete...Read More...Read More
We do work in Washington and Oregon as a subcontractor on commercial and public projects. Sometimes we are hired directly by the property owner. When required, can we send the preliminary notice before the job has started, at the time we book the job in our system or receive the contract? Are t...Read More...Read More
Does a subcontractor on a non owner occupied remodel that contracted for $10,000 materials and labor directly with the prime contractor have to provide the model disclosure to the owner? If not; it appears this subcontractor does not have to provide ANY notice, correct?...Read More