Menu
Home>Levelset Community>Legal Help>When does the clock start ticking on a MA Public Preliminary Deadline?

When does the clock start ticking on a MA Public Preliminary Deadline?

MassachusettsPreliminary Notice

Subject: Massachusetts Bond Claim Overview: Preliminary Notice Deadlines 20 Days None, unless furnishing specially fabricated materials. If so, notice must be delivered to the prime contractor within 20 days of receiving the order for the specially fabricated materials. Question: What is the date for receiving the order for the specially fabricated materials? Is this the date on that face of the PO or the later date when both companies sign, and date said PO?

0 replies