what is the start date of a new construction job? Is it from the time I deposit there deposit into my account?

Florida
Anonymous Subcontractor

I'm a manufacture that builds doors. when is my start date from when there deposit clears the bank or from shop drawing approval or when i start on building. we are always 2-3 weeks from starting any job after receiving a deposit because we are always finishing another job as i have this one line up to jump on once we complete last job.

1 reply

Attorney at Dinsmore & Shohl, Llp
| 168 reviews
Jan 13, 2021

If your doors are custom -- meaning they good not be easily used on another project -- then the start of construction or first furnishing of labor, material, or services, for the purposes of a notice to owner, is the date you start performing work. You have 45 days from that date to serve your notice to owner. But, you have from the day you sign the contract to that 45th day to serve the NTO, so I would do so earlier rather than later. 

The above comment/response posted by should not be construed as legal advice, establishing an attorney-client relationship, or as a solicitation for an
attorney-client relationship. Neither comments left on this website nor emails sent from this website are privileged or confidential. Do not take actiSee More...
See More...
0 people found this helpful
Helpful