I was hired by a contractor to provide service including labor and materials. And when I sent in invoice, he said he'll get me a check next week. When that failed to happen, I reached back out. And he gave me all these excuses of how there was a deposit put down on the property and they couldn't volleys the last check. So now he says he "promises" me that I'll get paid after they close on the house. Should I need to wait for closing??

2 replies

Attorney at Phillips & Angley
| 1 reviews
Dec 10, 2021
It is a business decision as to whether you choose to wait until the closing (or after) to obtain payment. You may want to consider placing a mechanic's lien on the project prior to the closing to protect your right to payment.
No attorney/client relationship is created by this answer and the answer is not intended to be relied on as legal advice to a specific person. No designation in
this website as 'construction lawyer' or 'real estate lawyer' or the like is intended to, nor shall it be construed as, my having a particular or out of tSee More...
See More...
0 people found this helpful
Helpful
Attorney at Eckert Seamans Cherin & Mellott LLC
| 6 reviews
Dec 12, 2021
If contractor was last on site in the last 90 days. , you can still lien within that time