We filed a lien on our job 2000 Bryant for $9K still owed to us. Today, we received a recorded Notice of Completion on this job. Is there any action we need to take to maintain our rights on this job?

1 reply

Attorney at Carlton & Alberola
| 93 reviews
Nov 13, 2020

You have 30 days from the date the NOC was recorded to record a mechanic's lien, but you've already done that. You have 90 days from the day you recorded your lien to file suit. If you've missed that deadline, don't fret, as you can record another lien, so long as you do so within 30 days of the day the Notice of Completion was recorded. Don't delay. Good luck.

Carlton & Alberola and/or Andrew Carlton have not been retained by the recipient of the above comment and, moreover, the above comment does not
create an attorney-client relationship. The above is general commentary based on limited and insufficient information. If you wish to obtain legal aSee More...
See More...
1 person found this helpful