how do i proceed to file foreclosure on a Lien i filled 45 days ago?

2 replies

Sep 22, 2022
Within 90 days of recording the lien you must file a lawsuit to foreclose on the lien. You should contact a construction lawyer. Good luck.
0 people found this helpful
Helpful
Sep 22, 2022
If you do not do so within 90 days of recording the lien, the lien expires.