Menu
Home>Levelset Community>Legal Help>How long do I have to wait to file a lien against the customer doesn’t wanna pay right then or do I have to wait a certa

How long do I have to wait to file a lien against the customer doesn’t wanna pay right then or do I have to wait a certa

Kansas
Anonymous General Contractor

How long do I have to wait to give notice of lien can it be at the moment the owner doesn’t want to pay or do I have to wait a certain amount of time

2 replies

Oct 24, 2020

In Kansas a lien can be filed once payment is due and not paid. Generally, if you are a contractor the lien must be within 120 days of last furnishing labor or materials and 60 days if you are a subcontractor. The time limits may differ if you are dealing with residential property.

This website is a public forum and no communication is private or confidential. Any answer provided is general in nature and no communication on this
website shall create any attorney client relationship.See More...
See More...
0 people found this helpful
Helpful
Oct 24, 2020

Correction:

In Kansas a lien can be filed once payment is due and not paid. Generally, if you are a contractor the lien must be within 120 days of last furnishing labor or materials and 90 days if you are a subcontractor. The time limits may differ if you are dealing with residential property. 

This website is a public forum and no communication is private or confidential. Any answer provided is general in nature and no communication on this
website shall create any attorney client relationship.See More...
See More...
0 people found this helpful
Helpful