Menu
Home>Levelset Community>Legal Help>How can I defend or reject the back charges ?

How can I defend or reject the back charges ?

CaliforniaBack Charges

We have project for channel earth works as a sub contractor,we finished the excavations,trimming and compaction for side slopes. All the work has been done according to the drawings and accepted by consultant. The inspections was for FDT and surveying works. I found some acceptable differences according to specifications for the surveying works (tolerance) of bed preparation (5mm - 15mm) The channel lining with concrete for 75mm. The contraction engr. of main contractor didn't accept the works while the works was approved,Most of the repair were to correct faulty level by Subcontractor, yet back charges were applied on subcon. without prior notice.

3 replies

Sep 11, 2019
I think it is safe to say that you need to consult with a construction lawyer as soon as possible to help you determine your rights, duties, and obligations to try to protect your position. ---CN
0 people found this helpful
Helpful
Aug 19, 2020
i have received an email from my main contractor , that he will bacjk charge on my and deduct the amount from my account for the load calculation of the ceiling system . knowing that : he didnt ask me to do the calculation test other wise i would have done it in free . how to send him a proffessional rejection letter for the charge back request .
0
Report Spam
Aug 19, 2020

You should send a detailed letter to the Contractor disputing the back charges and explaining why they are not warranted under the subcontract. You should include the technical argument as to why your work complied with the plans and specs, as well as making the point that you had no opportunity to correct any issues with the work.

1 person found this helpful
Helpful