Hi, We are a mat'l supplier. Our customer has not paid their inv., 90+ days delinquent. The project is Public, Golden Gate Bridge.
Yes, you can serve a stop payment notice to assert a lien on the construction funds in the hands of the public entity for the value of your materials furnished to date; you should also explore asserting a claim on the payment bond for the project. If you do not have the bond information, you should be able to get it from the public agency.
--CN
NOTE: The information presented here is general in nature and is not intended nor should be construed as legal advice for any particular case or client. The content contained herein is published online for informational purposes only, may not reflect the most current legal developments, verdicts or settSee More...See More...
1 person found this helpful
Helpful
Jun 12, 2020
Hi Christopher, Thank you, very helpful! Sincerely, Pam