I am trying to fill out the G703 and G702 forms but this is my final bill all work has been complete. I have watched the you-tube video but nothing shows how to do the final invoice so you can get the retainer back.

1 reply

Sep 9, 2020

Hello,

Without seeing your specific paperwork situation, 100% of the value of the work should be claimed as completed. The amount that you are requesting is the last piece plus any retainage. The balance remaining should be $0. If you need, include a letter saying that all work has been completed, including punchlist items, and you are requesting the balance of the funds owed to you including retainage.

E. Aaron Cartwright III
214.789.1354
Aaron@EACLawyer.com

I am an attorney but I am not your attorney... yet. The information provided here does not create an attorney/client relationship.
See More...
1 person found this helpful
Helpful