finialed my permit did not get paid so sent a notice of intent to lien how much time do I have to file a lien ?

FloridaLien Deadlines

Completed my job and finaled my permit on 12/9/2020. sent notice of intent to lien 01/07 2021 with no response the lien was filed 03/15/2021 is the lien filed late ? Is it 90 working days or 90 calendar days

1 reply

Nov 8, 2021

It looks like your lien was late. You have 90 calendar days from your last day performing work on the property to record your construction lien. 

Even though you may not have a construction lien right, you are still entitled to be paid. You should consult with an attorney to see what other options are available to you for payment. 