I performed a small concrete job at my home. The material supplied was not the correct color spec. I requested the concrete company to remove the product but the declined. 41 days later I received a preliminary notice of Lien. I sent a demand letter for resolution to the company owner and then 93 days after said delivery I received a lein notice filed on my house. This is holding up a refi. What can I do