I'm about to file within my lien right date. I just wanted to know if I could include the costs to file and discharge. I can also include interest

1 reply

Jun 29, 2021
You cannot include these items in a construction lien. Doing so could very well support a fraudulent lien claim. The lien may include "work performed" and "materials supplied" to improve the property.