My GC sent me a preliminary notice to lien towards the end of the project due to dispute in cost of work done (Time and Material Contract).
Can he do that now?
1 reply
Feb 4, 2021
If you did not get notice under RCW 18.27.114 (I am assuming you are not a contractor, but an owner given the nature of your question) then no. The contractor can still make contractual claims (as can you).