I am a GC working on a home. The homeowner has done a 180 and is refusing us access to complete work per contracted scope. My contract includes requirements of : "Customer’s Obligations: Customer agrees not to hinder or delay CONTRACTOR from performing the Work. " Can I terminate for cause without a contract clause outlining termination options?