I jus did a 73 hour tile job making twenty bucks an hour it's been a week since the job has been done and I still have not been paid.

1 reply

Attorney at Ostergar Lattin Julander LLP
| 44 reviews
May 11, 2020
If you had a direct contract with the owner or served a preliminary notice, you likely have lien right. If your work wasn't the entire project, you may have to wait until the entire project is complete before recording a lien.
Disclaimer: Any responses to questions do not create an attorney client relationship, and until a retainer agreement is signed no response should be
considered legal advice to a client. Email - tjulander@ostergar.com. Phone - 949-305-4590.See More...