The prelim was sent late. Can I still file a lien?
1 reply
Jul 14, 2021
A preliminary notice covers all work, labor and services provided within twenty days of the date the notice was sent. So, your lien can include all of the costs you incurred from the date of your notice, plus twenty days back. I suggest you have a lawyer experienced with construction claims assist you with determining the amount of your claim.