I just received an NOI from a handyman we hired. He quoted us a price of $200 and said it would take him a day to a day and a half to finish. On the third day, work was still not done! At that time, we gave him $100 (I have a signed receipt from him) and told him we would give him the $100 balanc...Read More...Read More
This question is probably not one you are used to getting but here goes: I see your site is primarily for general contractor's, but I am being harrassed by a Pool Service company (so she is not a GC, but rather she provides a 'service') who is threatening to put a lien on my home over $75. Her busines...Read More...Read More
Im a sub for a sub that did work on a government project on Nellis Air Force Base in Las Vegas Nv. The last day we worked was on was April 20th, 2019, the job was put on hold due to mold being found in the dorms . We were originally supposed to just open the fire chases and walls to give the plumb...Read More...Read More
Im a sub for a sub that did work on a government project on Nellis Air Force Base in Las Vegas Nv. The last day we worked was on was April 20th, 2019, the job was put on hold due to mold being found in the dorms . We were originally supposed to just open the fire chases and walls to give the plumb...Read More...Read More
The job was never finished but there has been no work or materials to the site for about a year. No demand for payment and no lien rights notices have been given. Have the lien rights expired? And do I have to formally finalize the job in any way?...Read More
I am a contractor and started work on a project. The client stopped us from working and is refusing to let us finish and not paying us for what has been completed. We have filed a notice of intent. How long do we have now to file the actual lien? ...Read More
our attorney placed the case with LevelSet for preliminary notice associated with huge project in Nevada. in California, an amount is normally entered on the paperwork and sent to customer, is this the case in Nevada? please advise...Read More
I’m a subcontractor in Nevada. I did work for a home preservation company based in Dallas Texas. They have a net30 day policy and it’s been well over two months. I put a lot of time and effort into this job,money out of my pocket as well which is why I feel like I just can’t let that slide ...Read More
I am filling out this form and am not sure if on the second page is where the owner of the company who is going to file the lien signs as the Agent of Claimant or if it has to be a third party....Read More