Arizona Preliminary Notice Questions

All Status
Preliminary Notice
Arizona
Is filing on a commercial property different from residential?...Read More
Anonymous Contractor
1 answerAdd commentJul 8, 2020
ArizonaPreliminary NoticeRight to Lien
Will preliminary notices with the lender information as "request" protect general contractors' lien rights? ...Read More
Anonymous General Contractor
2 answersAdd commentJul 8, 2020
ArizonaPreliminary NoticeRight to Lien
Our owner for a project in AZ said she received our pre-lien notice but asked if our CEO needed to sign the back or if it is just for her records? I'm not familiar
with this but is there a signature point on the back of this notice? Does she need to do anything with it? Thank you
...Read More
Anonymous General Contractor
1 answerAdd commentJun 17, 2020
ArizonaPreliminary Notice
We hold the property as an LLC and yet we received two prelien, one to the LLC the home is held in and then to my husband and myself in our names. Do I
have to return both? We do not want to be individually responsible hence the LLC. Please advise! Thank you ! Diane winter
...Read More
Anonymous Contractor
1 answerAdd commentJun 10, 2020
ArizonaLien DeadlinesLien WaiversPreliminary Notice
How can we still file a Lien if we did not prelien...Read More
Anonymous General Contractor
1 answerAdd commentJun 4, 2020
ArizonaPreliminary NoticeRight to Lien
My company works on large single family subdivisions. There may be 500+ lots in a subdivision. Are we required to send individual 20 day prelims for each lot
or may we send one prelim for each parcel/subdivision as long as we list the lot numbers, location and price? Each lot is priced the same. Each o...Read More
...Read More
Anonymous Contractor
2 answersAdd commentApr 30, 2020
ArizonaPreliminary Notice
We never preliened this job and we haven't been paid since December. Justin suggested sending a notice of intent but how can I do that when we never sent
them a preliminary notice. The GC is saying because of corona virus payment has not been seen.
...Read More
Anonymous Subcontractor
2 answersAdd commentApr 21, 2020
ArizonaNotice of Intent to LienPreliminary NoticeRecovery OptionsRight to Lien
Working at a residential home, start date is 10/22/18, end date actually in home was 3/19/20, worked remotely in house 4/2/20 for programming AV. Do I
need to prelien?
...Read More
Anonymous General Contractor
1 answerAdd commentApr 14, 2020
ArizonaPreliminary Notice
If I am a supplier of construction materials do I have to send the 20 day preliminary notice in order to have the right to file a lien later? If the 20 day has
passed but I am still within the 120 day period do I as the supplier of materials still have the ability to file a mechanics lien?
...Read More
Anonymous Contractor
1 answerAdd commentApr 6, 2020
ArizonaMechanics LienPreliminary Notice
I am doing a commercial job. Almost 4 months into the job now.I have gotten played for 3 draws but on April seven he said he could only pay $35,000 of a
79,716.35 invoice of work already done. He said that thats all he had in his bank account. He told me he would get the loan for the balance in on...Read More
...Read More
Anonymous General Contractor
1 answerAdd commentMar 28, 2020
ArizonaCoronavirusPreliminary NoticeRecovery Options
We are starting a job at the Grand Canyon remodeling resident housing owned by the National Park Service and would like to file a 20 day prelim mechanics
lien
...Read More
Anonymous General Contractor
1 answerAdd commentMar 12, 2020
ArizonaMiller ActPreliminary Notice
We installed some palm trees as a subcontractor on a city job back in June & July 2019 and we have not been paid yet. Thank You...Read More
Anonymous Contractor
2 answersAdd commentSep 17, 2019
ArizonaPreliminary NoticeRight to Lien
I have 4 contracts for one project. I am in the process of doing a bond claim. I did a pre lien on 2 of those contracts, can I included the total dollar amount
due in my bond claim?
...Read More
Anonymous Subcontractor
1 answerAdd commentMar 3, 2020
ArizonaBond ClaimsPreliminary Notice
We're in a bit of a sticky situation! We had 4 contracts total for a large AZ commercial job. We sent a prelien for the 2nd and 3rd contracts, but not the 1st or
4th. Everything that we are owed is for retainage or change orders, but I'm worried that I can't file a lien for funds I didn't prelien. Should I have s...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentMar 3, 2020
ArizonaChange OrdersConstruction ContractMechanics LienPreliminary Notice
I work in the service department for electrical commercial contractor. We propose repairs that could go as high as 5K however we do not enter into a
contract/written agreement. Can we file a pre-lien?
...Read More
Anonymous Contractor
1 answerAdd commentFeb 27, 2020
ArizonaPreliminary Notice