I did some work for a local motel and I am still owed 750 bucks ,I did the job a year and a half ago and the motel has been sold and tore down,since then,but I recently found out that the owner bought another motel here in town,so I stopped by and the owner refuses to pay me,do I have a chance of getting the money I am still owed or should I just forget about it...Read More
Anonymous Contractor
2 answersAdd commentJul 24, 2020
TexasLawsuit
2 Mechanic's liens were filed on my property. The law suit was filed, but I was not served. I learned this 6 months later and just learned of the lawsuit this year in 2020. The liens are improper....Read More
Anonymous Contractor
1 answerAdd commentJul 21, 2020
CaliforniaLawsuitLien ReleasesMechanics Lien
I received notice that my AC guy is trying to place a lien on my home for $4000. I had already filed a small claims suit for $4900 but I am still waiting on my case to be given a case number. I had to fire him because he didnt know what he was doing. What are my options?...Read More
Anonymous Contractor
1 answerAdd commentJul 7, 2020
New YorkLawsuitMechanics Lien
Can I sue a salesmen manger who is now stealing clients ...Read More
Anonymous Contractor
1 answerAdd commentJul 7, 2020
OklahomaConstruction ContractLawsuitRecovery Options
Good morning, I am inquiring about removing a lien in Illinois. Here is the super short version of the situation. Contractor placed a lien on the house. I sent a Demand Letter under Section 34 of the Illinois Mechanics Lien Act. The contractor did not file suit within the required 30 days. The questions I have are: 1. Is there a way that I can remove the lien without taking the contractor to court? 2. How long will the process take? 3. What is the quickest way to get the issue resolved?...Read More
Anonymous Contractor
1 answerAdd commentJun 30, 2020
IllinoisLawsuitLien ReleasesMechanics Lien
On Aug 19 2019 I started re-designing a deck for Nancy Thompson. There when many delays with wood choice and deck stain color. 2 weeks into project the weather became a factor as it rained often. I continued to work on her deck through Dec 8th 2019. The only Items left to do was sand, stain deck and a few trim pieces. I made a revision change to the contract to restart in around May 1st 2020 pending weather availability. it rained at least 2 days a week through may-june 2020. I had not receive any replies to email or text so I check out her home to discover her deck finished and stained, house up for sale. do I have a legal leg to stand on or not?...Read More
Anonymous General Contractor
1 answerAdd commentJul 1, 2020
WisconsinLawsuitMechanics LienRecovery OptionsRight to Lien
I filled a lien as the main contractor what do I do now ...Read More
Anonymous General Contractor
2 answersAdd commentJul 11, 2020
TexasLawsuit
What to do if a shady mechanic puts a mechanic lien on your vehicle? The vehicle repairs were all paid in advance, but has not finished the job in over 7 months. Now, the mechanic is holding the car hostage and won't let it go, claiming he has all the time he wants to finish the job. (and can add more fees if they want.)...Read More
Anonymous Contractor
1 answerAdd commentJul 13, 2020
TexasLawsuitMechanics Lien
I have a contractor that is threatening to put a lien on my property. She claims i owe her money after I fired her for wrongful charges and made up numbers and not completed work. I have evidence of it all and I had to pay another contractor to finish her work. If she files a lien how can I cancel her lean or remove it without paying her?...Read More
Anonymous Contractor
1 answerAdd commentJul 13, 2020
TexasLawsuit
We did an installation at our customer's property and they claim that we did damage to their building. They are withholding 41K from us because of their "claim". After numerous attempts and over half a year of trying to get any proof to back up what they are accusing us of, they have not provided and other info. Recently, they contacted us for service and gave us an ultimatum of paying half of the outstanding balance as a final settlement, or they would pursue litigation. We believe we did not do anything to that building so we are not giving up 20K just like that. They have many other mechanic liens under their company so we believe their claim that we did damage is just them trying to get out of paying or just getting a cheaper deal. What should we do?...Read More
Anonymous Subcontractor
2 answersAdd commentJul 10, 2020
CaliforniaLawsuitRecovery Options
I recently finished building a custom home. I had a contract with a GC but did not have any contracts with any subs, just bids. None of the subs filed a pre-lien. I paid all the subs directly, the GC did not. The electrician gave me a bid of $27K to provide all the materials/labor to rough and trim out the house except the actual light fixtures. I actually performed 30-40% of the labor and purchased about 40% of the materials for rough in. I paid the electrician $16K in cash at the end of rough in. At trim out I performed 90% of the labor and provide 98% of the materials. My electrician sent me a bill for $8500. I told him this was ridiculous and I wasn't paying him 24.5K for a job where I did a lot of the labor myself and purchased most of the materials he was supposed to. I told him I would give him an additional $1K cash but that was it. He threatened to sue and file a lien on my property. The completion of the project is over 90 days, my COO is over 60 (fighting with the city on a drainage issue held it up) and my recorded notice of completion is over 30 days old. Without a pre-lien and no contract what recourse does he have, if any? ...Read More
Anonymous Contractor
Waiting for answerAdd commentJul 8, 2020
CaliforniaLawsuitLien Deadlines
I am the homeowner who signed a contract for someone to remodel my home after it was damaged. contract stated all materials and labor were included in the quote.Only way they can change is if it was in written request. We are at the end of four months on a two month job. Contractor is trying to force me to sign a new contract for my insurance to pay more and for me to pay more. I was threatened that if I do not pay the difference if they will put a lien on my home and remove stuff from my house they put in here. My insurance company refused to pay any more instead of the Contractor saying they’re going to sue me even though they have not finished the job. I have copies of the contract, photos, and voice recordings of conversations of threats of placing a lien on my home....Read More
Anonymous Contractor
1 answerAdd commentJun 23, 2020
TennesseeLawsuitPayment DisputesRight to Lien
I hired a contractor to remodel three bathrooms. I refused to pay him the full amount because of shoddy work (eg one of his subs damaged a wall and it was not properly repaired incorrect work (he used the wrong color grout in one bathroom, did patching jobsand textured walls that had been virtually smooth, etc. We discussed a compromise but did not reach an agreement, and he kept making up new charges for things we never agreed to The unpaid balance is $3862, but he placed a lien for $10280. Included in that amount is recording the lien and interest. If it goes to foreclosure can the lien be enforced? And if so, can we prevent foreclosure by paying what the court says we owe? ...Read More
Anonymous Contractor
1 answerAdd commentJun 29, 2020
CaliforniaLawsuitMechanics Lien
A customer of mine asked to use my tractor for some light work on his property. He cracked the boom and broke the hydrolic arm. Is he liable for the whole repair? I own a septic and plumbing company since 2006 but have been going through a divorce since 2009. I informed the property owner my licence was not active I was there as a subcontactor. The home owner was responsible for all permits. The work I did there on his property took over 6 months to complete. I also have a study job at the home depot. I would leave my tractor there and come up on the weekends to do work the homeowner requested. I put in 2 septic systems with no problems. I got a call from his "Forman" asking if he had permission to move some dirt. I said it was ok . Later on that day I got a call from the forman telling me that when he was driving it to put air in the tire the back arm was swingging and ready to fall off. The hour meter shows the tractor was running for three hours. I spoke with a equiptment mechanic and farm equiptment expert on justanswer.Com who told me that the only way the damage to the boom could of happend was somebody used the tractor and tried to carry way beyond the load compacity which was 11,000 pounds. The work I did there didnt exceed 800lb load. The home owner had large stone bathtubs on his property. I believe they tried to move them with my tractor. I left my equiptment there because the homeowner had installed a security system and cameras all over his property to watch his employees. He claimed the cameras were not on that day. He claims no responsibility for what happened. It has been almost a year and he has offered me no more than $1500.00...Read More
Anonymous Subcontractor
1 answerAdd commentJun 13, 2020
CaliforniaLawsuitPayment DisputesRecovery OptionsRight to Lien
As the Material Supplier, we filed a bond on the public property (K09863-19.1) is the project id in our Levelset account. We were later notified of updated BOND information. Erin Classen suggested I reach out to your to inquire what our next step since their BOND CO has since changed in the midst of the project....Read More
Anonymous Material Supplier
1 answerAdd commentJun 19, 2020
TexasBond ClaimsLawsuitPayment BondPayment DisputesRecovery Options