Regarding Class 4C apartments in New Jersey. If the subject is a proposed development of say, 24 apartment units for rent with no retail at ground level, is
the subject "residential" or "commercial" for lien purposes? Notes: project still under construction. No CO. Prior class was 15D, religious (demolished).
...Read More
Anonymous Subcontractor
Waiting for answerAdd commentOct 28, 2022
New JerseyMechanics Lien
Im a fencing subtractor and finished a project back in September of 2021 and the company has not paid me as of yet. I already did the Notice of Intent with
you all and Nothing. Also hired a lawyer who sent a letter and Nothing. Thousands of dollars paid to lawyer for nothing to happen. What can I do...Read More
...Read More
Kenneth Hammond
2 answersAdd commentAug 27, 2022
New JerseyLien WaiversMechanics Lien
We are an Operations & Maintenance provider and the GC of the project wants to include the following clause in the contract, "Contractor shall not place any
Lien or other encumbrance on the Facilities or the Sites." Can
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 14, 2017
New JerseyConstruction ContractLien WaiversMechanics Lien
I am signing a subcontractor master agreement. within states: general release and waiver of lien rights. I need to submit the subcontractor agreement in
order to receive work. If I sign this can I still lein if I do not get paid?
...Read More
Anonymous Contractor
2 answersAdd commentJun 14, 2022
New JerseyMechanics Lien
I recently sent out a Notice of Unpaid Balance in association with a residential construction lien in NJ - where we also have to file an Arbitration Demand
Letter. I noticed that the Arbitration Demand requires a "Number Book Page" to be included. Does this information come from the county clerk's...Read More
...Read More
Advanced Professional
Waiting for answerAdd commentMay 20, 2022
New JerseyMechanics Lien
We are a NY millwork company selling doors and mouldings, we have a customer in NJ that we delivered goods back in September 2021 and we haven't
received payment, we still have custom doors, meaning doors that we usually don't stock we just ordered and assembled for them but we did no...Read More
...Read More
Anonymous Material Supplier
1 answerAdd commentMay 5, 2022
New JerseyLien DeadlinesMechanics Lien
Did water mitigation here in the amount of $19,402.43. Have not been paid since 7/20/21...Read More
Brian Bromberg
Waiting for answerAdd commentMay 5, 2022
New JerseyMechanics Lien
Good afternoon. We're trying to find out if the mechanic's lien we're filing is residential or commercial in nature. The property is a residential structure that is
owned by a bank/trust and managed by a property management company that rents the property out to tenants. Thank you so much for your help!
...Read More
Advanced Professional
1 answerAdd commentMay 2, 2022
New JerseyMechanics Lien
Hello! We are materials supplier on the project in NJ, and we want to file Lien. In our agreement with the client and on architectural set we have on file, we
found owner name, but levelset scout research indicated other company as owner. What we should do in this situation? Can we include both com...Read More
...Read More
Anonymous Material Supplier
1 answerAdd commentMar 31, 2022
New JerseyMechanics Lien
Can a mechanics lien be filled for licensed remodel work (a renovated bathroom where the project is complete, for example) where a lending agreement is in
place? In other words, where the homeowners agreed to a payment plan - can that loan be secured by a mechanics lien where the contractor w...Read More
...Read More
Anonymous Contractor
Waiting for answerAdd commentFeb 14, 2022
New JerseyMechanics Lien
I am levelset subscriber. I am the drywall subcontractor on a project. My work is completed back on 11/9/21. People are already moving in to the units and I
still have not been paid my final payment by the GC. I need to know the details on how to file this lien as it is state funded.
...Read More
Steve Albanese
2 answersAdd commentFeb 2, 2022
New JerseyMechanics Lien
Im a GC that finished my job on the 10th and want to get paid. I sent an email demand through you guys, whats the next step? state of NJ...Read More
john powers
1 answerAdd commentJan 21, 2022
New JerseyMechanics Lien
I was contacted and then issued a PO by the Clifton Public Schools to replace the wall safety padding in School 17 which was damaged by storm Ida. This was
an insurance claim filed with their carrier. After the work was completed the school/principal is refusing to pay the PO complaining about they wa...Read More
...Read More
Anonymous Contractor
2 answersAdd commentJan 20, 2022
New JerseyMechanics Lien
I did a project for a 2 story commercial building- part of a larger complex of condominiums Have a good written detailed agreement, finished the job,
emailed everything, they offered partial payment, I declined, offered to defer a little until permits release, but they have gone silent, so I think I s...Read More
...Read More
Anonymous Contractor
1 answerAdd commentJan 10, 2022
New JerseyMechanics Lien
Hello, There was damage done to my home. A construction company had me sign a contract that allowed him to accept money directly from the Mortgage
company. The company took 2 years to due the project and its still not done. In the middle of construction the Mortgage company issued a check...Read More
...Read More
Jess smith
Waiting for answerAdd commentNov 26, 2021
New JerseyBankruptcyBond ClaimsConstruction ContractJoint ChecksMechanics Lien