I filed a mechanics lien on a customer. They have not received insurance money and are going to pay me out of pocket while they wait for the money to come because they are very concerned about the lien affecting their credit score. I've read that generally, mechanics liens don't affect a credit score but what does that mean. When would it affect their credit score? He's very concerned and asking lots of questions and I want to make sure I can give him accurate and clear information....Read More
Anonymous Contractor
2 answersAdd commentDec 8, 2017
NevadaMechanics Lien
I was working in the ac company and when i was olmost finish the job i no recieve a payment and i buy somematerial but the contractor that i work he no claim the money for a general so im in the air can i claim togeneral...Read More
Anonymous Contractor
1 answerAdd commentSep 9, 2017
NevadaMechanics LienPayment DisputesRecovery Options
I did my mechanics lein, it was placed on the property but the homeowner abandoned the house, and moved out of state. The granddaughter is the trustee on the home and offered the home as payment, what do I do? Payments still have not been paid and the house is just sitting. Do I have the right to obtain possession? And file this with the state accessors? And legally own this home, ? Or can the granddaughter just pull a loan to pay the debt. Her credit is shot and is in a bad place and I need some answers to help me get this behind me and move forward...Read More
Anonymous Laborer
1 answerAdd commentMar 23, 2023
NevadaMechanics Lien
hello, I have three questions about preliminary notices in Nevada, 1- how early can I file a preliminary notice? 2- from when is it considered that we began supplying material, from when its on site or from when its in the warehouse? 3- to who do i need to send the notice to for it to be legally affective?...Read More
Nachmen Davis
1 answerAdd commentMar 6, 2023
NevadaLien DeadlinesMechanics Lien
i have not been paid from my last 3 invoices sent on Nov. 1st. 2020...Read More
Anonymous Subcontractor
1 answerAdd commentJan 25, 2023
NevadaMechanics Lien
We have a contract with a gc on a private commercial building. I am having trouble collecting information on the owner to file our preliminary notice but our contract mentions a bond (I also have not been given information on the bond company) do I still need to file a preliminary notice? How do I go about getting the information I need? What if they don't give me the information within the 20 days of starting work?...Read More
Anonymous Contractor
1 answerAdd commentJul 23, 2018
NevadaBonding Off LienMechanics LienPreliminary Notice
Hello, Have a customer where 31 day intent to liens were mailed with only the Subcontractor information, do I still have lien rights? Customer has not paid their bill and they are approaching the 90 day deadline from last shipment date. ...Read More
Anonymous Material Supplier
2 answersAdd commentJan 23, 2023
NevadaMechanics Lien
We filed for a notice of intent to be sent as well as a lien, but they sent them out of sequence. The lien has been sent to the recorder and the notice of intent has yet to be sent to the customer. If I understand correctly, it is mandatory that the notice of intent is received first....Read More
Nicholas Tilley
1 answerAdd commentDec 20, 2022
NevadaMechanics Lien
Hi Alex I read your very helpful guidance on Mechanics Lien on the Levelset website and would like your help if we go ahead but first I have a question on eligibility. We supplied lights to the value of $700,000 to a company in Las Vegas. The company has paid half the purchase price but is trying to delay payment of the remaining $350,000. The lights will be installed in the event space of one of the big hotels on the strip but at the moment they are in our client's warehouse. Here's the question: our client will lease the lights to the hotel on a long lease so the hotel will not own them. Can we claim that these lights constitute a permanent improvement to the hotel and register a lien on them? Best wishes Joe Ruston Director Remote Controlled Lighting Ltd London, UK...Read More
Anonymous Contractor
2 answersAdd commentSep 3, 2020
NevadaMechanics Lien
help with lien...Read More
Anonymous Subcontractor
1 answerAdd commentDec 22, 2022
NevadaMechanics Lien
I had a contract to do 30 homes they teeminated the contract didnt payi put liens in the last 12 they claimed they paid us and back charged us now claiming we didnt do any work onthe properties now try8ng to ger them expunged ...Read More
Anonymous Subcontractor
1 answerAdd commentDec 20, 2022
NevadaMechanics Lien
As a supplier, can we file a mechanic's lien in Nevada if the person we sold to is not the property owner, and is not a licensed contractor if the material in not paid for?...Read More
Anonymous Contractor
2 answersAdd commentOct 6, 2022
NevadaCollectionsMechanics LienMaterials
We were contracted for $299,925. We have been paid for $252975, leaving a balance of $46,950. This balance is for work we have yet to complete. We sent a change order for $53,431 for work that was not in the contract. We want to lien the project for that change order, however since that lien total is more than what is owed on the contract Levelset is unable to process the lien. Please advise....Read More
Caitlin Matthews
1 answerAdd commentSep 20, 2022
NevadaMechanics Lien
He took the motor home and is trying to sell it himself...I want to file a lean...Read More
Anonymous Contractor
Waiting for answerAdd commentMay 19, 2022
NevadaMechanics Lien
I have a contract with a property management group for painting of 6 buildings, the owners are refusing to let the property management group to pay after the work has been completed. How and who do I lien? Contract is under the management company working for the group of owners for the buildings....Read More
Anonymous Contractor
Waiting for answerAdd commentMay 10, 2022