I filed a mechanics lien on a customer. They have not received insurance money and are going to pay me out of pocket while they wait for the money to come because they are very concerned about the lien affecting their credit score. I've read that generally, mechanics liens don't affect a credit ...Read More...Read More
I was working in the ac company and when i was olmost finish the job i no recieve a payment and i buy somematerial but the contractor that i work he no claim the money for a general so im in the air can i claim togeneral...Read More
I did my mechanics lein, it was placed on the property but the homeowner abandoned the house, and moved out of state. The granddaughter is the trustee on the home and offered the home as payment, what do I do? Payments still have not been paid and the house is just sitting. Do I have the right ...Read More...Read More
hello, I have three questions about preliminary notices in Nevada, 1- how early can I file a preliminary notice? 2- from when is it considered that we began supplying material, from when its on site or from when its in the warehouse? 3- to who do i need to send the notice to for it to be legally affective?...Read More
We have a contract with a gc on a private commercial building. I am having trouble collecting information on the owner to file our preliminary notice but our contract mentions a bond (I also have not been given information on the bond company) do I still need to file a preliminary notice? How do I go a...Read More...Read More
Hello, Have a customer where 31 day intent to liens were mailed with only the Subcontractor information, do I still have lien rights? Customer has not paid their bill and they are approaching the 90 day deadline from last shipment date. ...Read More
We filed for a notice of intent to be sent as well as a lien, but they sent them out of sequence. The lien has been sent to the recorder and the notice of intent has yet to be sent to the customer. If I understand correctly, it is mandatory that the notice of intent is received first....Read More
Hi Alex I read your very helpful guidance on Mechanics Lien on the Levelset website and would like your help if we go ahead but first I have a question on eligibility. We supplied lights to the value of $700,000 to a company in Las Vegas. The company has paid half the purchase price but is trying to d...Read More...Read More
I had a contract to do 30 homes they teeminated the contract didnt payi put liens in the last 12 they claimed they paid us and back charged us now claiming we didnt do any work onthe properties now try8ng to ger them expunged ...Read More
As a supplier, can we file a mechanic's lien in Nevada if the person we sold to is not the property owner, and is not a licensed contractor if the material in not paid for?...Read More
We were contracted for $299,925. We have been paid for $252975, leaving a balance of $46,950. This balance is for work we have yet to complete. We sent a change order for $53,431 for work that was not in the contract. We want to lien the project for that change order, however since that lien total...Read More...Read More
I have a contract with a property management group for painting of 6 buildings, the owners are refusing to let the property management group to pay after the work has been completed. How and who do I lien? Contract is under the management company working for the group of owners for the buildings....Read More