I start this job and they make me sign a contract wich had not dead line to finish the job , the last day their supervisor came and told me they cannot wait for me to finish so they will take over t o complete the last details and they will deduct from my last payment wherever they spend on labor. I wait more than a week and I had not answer from the supervisor , so the last message I sent telling him that I will talk to his boss he answer that there's not balance for me because they owe me $3985 and they spent more than $5000 to fix those details . I spent around $3500 on labor and materials to paint this 2345 sqft house and also installed drywall in the bathroom, kitchen and living room. They contract said that I had to apply 2 coats of paint and I apply 3 ...Read More
Anonymous General Contractor
Waiting for answerAdd commentSep 27, 2022
ConnecticutConstruction Contract
I filed a mechanics lien in July for non-payment of completed work. Will I need to extend the lien to keep it active in 1 year?...Read More
Anonymous General Contractor
2 answersAdd commentSep 16, 2022
ConnecticutMechanics Lien
homeowner, wants monies back after we started work and scheduled are time, for this job, and wants an invoice for work done....Read More
Anonymous Contractor
1 answerAdd commentDec 4, 2020
ConnecticutConstruction Contract
I am a self employed sub contractor of entertainment (musical) performances at nursing homes in the States of CT and RI. My issue is in reference to one my CT based clients, for which I do programs at 5 of their facilities in both CT and RI. I know that I am not the only entertainer that is having issues in collecting. I have a date going back to April 2019 and a different facility for June 2019. The rest are monthly performances beginning with September 2019. They are now 6 months is arrears. The email address on their website is incorrect. I did obtain an email address to which I sent a respectful letter several weeks ago, with no response. This site appears to pertain only to Construction job, is that correct or does it also apply to other vendor situations? Thank you for your time and any information or direction you can provide. Sincerely, Judy Hall Gray, Hope Valley, RI...Read More
Anonymous Contractor
1 answerAdd commentMar 1, 2020
ConnecticutCollections
I have a lien filed against me on my home for masonry. ...Read More
Daniel Witkins
2 answersAdd commentAug 1, 2022
Connecticut
Are custom made motorized shades and blinds lien able fixtures? They were adapted and modified to fit a particular space and permanently attached to the window. These fixtures (blinds and shades) are considered part of the house in real estate, not personal property. Thank you!...Read More
Anonymous Contractor
3 answersAdd commentAug 1, 2022
Connecticut
We installed shades in a home. Real estate law says these are fixtures (real property). Client will claim they are personal property and we don't have right to file a lien. Who decides that and when is it decided? ...Read More
Anonymous Contractor
Waiting for answerAdd commentAug 1, 2022
Connecticut
Thank you. Client is going to contest the validity of the lien (he is a lawyer, haha) Is that when I would add more detail? How does that part of the lien work?...Read More
Anonymous Contractor
1 answerAdd commentAug 1, 2022
Connecticut
I read the importance of correct claimant name after I printed and notarized the Notice to Lien. Can I add "my name dba" (handwritten) next to my business name (that is typed in the notarized Notice)? Do I need to initial next to the handwritten portion? Will the Notice have to be rewritten and resent? The Certificate to file with the town clerk will have the proper typed name as claimant. I'm on vacation and can't get a new notary and don't want to miss a deadline. ...Read More
Anonymous Contractor
Waiting for answerAdd commentAug 1, 2022
Connecticut
Is a simple description of work in the Notice to Lien adequate? Should more detail go into the actual Certificate of Mechanics lien that is filed with the town clerk? ...Read More
Anonymous Contractor
1 answerAdd commentAug 1, 2022
Connecticut
I am a licensed HVACR Connecticut Contractor.9 months ago I placed a mechanical lien on a property. Materials and labor were supplied to a (supposed) friend of 17+years where as a boiler, gas piping and hot water system were installed in his girlfriends home, Subsequently she became his wife. When the now husband was presented with a already discounted bill he refused to pay. We have spoken several times and he has made me offers for less than what the material cost me, this was unacceptable and only after I filed suit against him, his girlfriend and her father did he reach out to me to settle. I filed two small claim suits as the amount was greater than $5,000.00. I withdrew the suit as enforcement (Foreclosure) of the mechanics lien in place may wake him up and entice him pay. It is not worth the expense to litigate in superior court as the cost to defend my position could exceed the amount owed with no guarantee my collection efforts( Legal fees) will be compensated for....Read More
Anonymous Contractor
2 answersAdd commentJun 5, 2022
ConnecticutMechanics Lien
file for a lien on a property for non payment...Read More
Sadrac A L
1 answerAdd commentMay 26, 2022
Connecticut
I am a material supplier on a commercial construction job. The owner is having issues closing on funding the complete the project at approximately 50% complete. I have supplied 99% of my contract and the date we last shipped equipment was 3/12/21. We still owe them 79 components to complete our deliverables. The general contract has promised to pay $10k for June and July so we can reduce our receivable balance from $92,315 to 72,315. Should I file a lien now or wait to see if the general delivers the $10k in June and July before filing?...Read More
Anonymous Material Supplier
Waiting for answerAdd commentMay 25, 2022
ConnecticutConstruction Contract
I'm in New Haven CT. and I would like to enforce a Mechanical Lein. How much are your services and what is the process and total costs?...Read More
Anonymous General Contractor
3 answersAdd commentMay 17, 2022
ConnecticutMechanics Lien
My clients are trying to sell their house. If my mechanical Lein is active can they sell their house without paying me?...Read More
Anonymous General Contractor
2 answersAdd commentMay 17, 2022
ConnecticutMechanics Lien