The copy is stamped as such. My client requires an unconditional final waiver of lien, to be handed to the Title Company. It can take a week or two before the latter releases the final payment. The owner of my company is reluctant to sign such a document, before receiving the final payment. Our client ...Read More...Read More
We were hired to do electrical work in the common areas of a condo association. Work was completed in November and invoiced in November; invoice remains unpaid, and we are closing in on 4 months. Does the lien get filed against the association, or the individual owners?...Read More
Hi, I filed a mechanics lien on a property, it just for 18k and the condo it’s valued at 2.5 M. I also would like to filed a civil law suit against them for the working conditions I was forced to work under and the treatment received....Read More
If I am currently working on a project and have not received payment, Would I have to stop working completely in order to send a letter of intent to lien or mechanics lien? Would are the right steps to take, and can they back charge me if I do stop work due to non-payment?...Read More
I have built a home and the contractor gave me an extra bill for work he said he did throughout the 12 months of building my home. I had a 6 month contract which states he has to provide estimates up front for any extra work that he would do to the property that must be signed off by both parties. He...Read More...Read More
Our customer was renting our equipment for work that he was doing as a sub-contractor on a construction site and significantly damaged the rental equipment. Per the rental agreement, the customer is responsible for 1. rent while the equipment is being repaired 2. loss of value of the equipm...Read More...Read More
I was contracted by OW2 Construction to paint at 8235 S. Cornell and was only paid $1500 of $7000 I was supposed to be paid. I did not have a contract, but I do have text messages outlining the agreement. I need assistance in knowing what I need to do next....Read More
I am about to file a 90 day lien notice in Illinois. It suggests to certified mail the documents to the defendant. Can I tact on the cost of the certified mail to what is owed to me....Read More
We did a project on 04/01/2021 for Continental Construction in which we received a small portion of payment leaving a balance of $50K in which the client is no where to be found, he doesn't answer calls. ...Read More
I am a property owner of an apartment building in Illinois, one day i got a Notice of Intent to File Mechanics Lien When i called the company who send the letter, they said they provided board up service to one apartment, but they don't have any documentation of the service agreement or contract. ...Read More...Read More
Cook County, Illinois: We did a roof job for a homeowner and he is unable to pay now. He is currently in Ch. 13 bankruptcy. Can we still file a mechanics lien here? Thank you in advance! -Joe...Read More
We are based in IN and we have a customer in IL. There was no signed contract or preliminary notice, but we do have the customer's signature on a change order from mid-job. Is there any way to file a partial lien on the amount of the change order? The work was done in 2019. Have we missed the wi...Read More...Read More