Supplied materials and labor and made return trips and finally picked up the temp power pole in July. What are we able to do at this point? Just signed up with you guys, we have requested payment to no avail...Read More
We are a Florida business that sold furniture, including installation, to a North Carolina business and the North Carolina business has not paid the final bill, about $25,000. The last time we were at their facility was April 29, 2022. What do I need to do? What should I be aware of if I file a lien? Can I retrieve my furniture after I file a lien? ...Read More
having a new house built on property i purchased. took out va loan. house burned down 2 days ago. i had no builders risk insurance because va lender say it is builder who has carry it through construction phase. builder now tells me he is not liable? fire under investigation but builder tells me he has no insurance it was my responsibility. i have 400,000 invested in this. can you help me out what i should do...Read More
Realtor reached out said she needed help to turn this project in and put it on the market. The home owner ran us off the job a day before the last day of work and claims i didn’t finish and that for that reason he doesn’t have to pay me. ...Read More
I have done about 80k worth of improvements to a home my dad has promised to sell me. He no longer wants to honor that. We have no written lease, no agreement for improvements, and no documentation that he said for us to buy it. However my mom does remember him saying that and can witness to the agreement. We have completely transformed this place! New siding roof deck kitchen 2 bathrooms flooring painting in and out new doors and the list goes on. What can I do?...Read More
I am a drywall & painting subcontractor, that I did a job to SAMET Corporation in a project in Raleigh, NC, I did lien the property, and also, I been contacted by SAMET layer saying I own SAMET money, and also, they want to go to Arbitration. SAMET attorney is Brett M. Becker from Nexsen Pruet, PLLC. That is a easy case, I have lots of proofs on my favor and they breach the contract. Somebody contact me by email and I will feel it up with more details.
Thanks...Read More
We did time and material work for Brantley Construction. They issued us a po based on time and material but not a specific dollar amount. We sent a total of 5 payment apps with the last one being on 11/12/21. We were paid for the first three apps. There has never been any contact about any problems with the work or the billings. I am getting excuses every time I actually hear back from them. The last time was on May 11th when I was promised that payment would go out that week.
What can we do to collect this $20,510?
Thanks....Read More
We are a general contractor working on a residential project. We just fired a subcontractor for failure to perform service to our agreed upon quality standard. The issues are well documented and have been continuous throughout the project. We paid them for all work done so far, but reduced the 3rd draw payment by the value of the labor and materials to repair some of their many mistakes, and docked them the field supervisor fees for the third draw of the contract as they had not actually supervised the field, resulting in many issues. The errors were significant and expensive. They have not signed a lien waiver. We realized walking away that we should have had them sign one before we paid them. We have never had to fire a sub before. We have an arbitration agreement in the contract....Read More