We are a provider of flooring goods and services to the multi-family industry in the Southwest. A key client has asked us to provide goods and services to a new construction project in Florida with an initial value of $400,000. We have licensed ourselves to do business in Florida, but as the one responsi...Read More...Read More
long story short we just sent a 10 day notice to pay to our mortgage company and letting them know if we are reimbursed for monies that were put in the property they can keep the property. However after the 10 days and they don't respond we can place a lien on our property correct so it was to ...Read More...Read More
The company I sell for supplies floor and roof trusses to builders in South Florida. (2 progress payments) We shipped floor trusses to Buildings 4 and 5. We received payment and issued partial waivers for those specific amounts. In the next pay cycle we shipped building 5 roof trusses but not Building ...Read More...Read More
Delivery of equipment was on a Friday, began work on following Tuesday and completed the job 20 days after work began or would it be 24 days from equipment delivery. I did not file a NTO, and GC is not paying me for work performed. Can I still file a NTO?...Read More