Washington State homeowner has paid contractor (our customer) in full. We have not been paid by contractor and intend to file a lien on the property. Owner
will dispute our lien based on his payment in full to contractor. My most up-to-date info is from 2019 and I would like to have more recent confir...Read More
...Read More
Ayla Gokturk
1 answerAdd commentFeb 13, 2023
WashingtonRight to Lien
Levelset did a 'notice of claim on bond'. Customer now wants to pay us, but needs something signed releasing bond. I was told by Brandon that this was a
public bond and there was not a filed document. What do we need to provide to customer to release this bond. We are an Oregon company, but ...Read More
...Read More
Accounting Department
1 answerAdd commentFeb 20, 2023
Washington
The contract and building has new owners and a ''receiver" Can I add them to this mechanics lien? We still have not been paid the outstanding $28K...Read More
Anonymous Subcontractor
1 answerAdd commentFeb 15, 2023
Washington
This is a large project on public land (a new community essentially) Yet the "Owner" of the project is an LLC. The job has gone south. They lost an arbitration
award of 11.49 million as they were found to have "actual intent to defraud Lender:). The lender supplied 66 million in funds of 132 investors. We...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentDec 7, 2022
WashingtonBond ClaimsMechanics Lien
How long does a Lien last in WA state? We have filed our lien and the owner is working to get it resolved. However, both our supplier and us claimed the
materials owed. The Owner obviously doesn't want to pay for materials 2 times and has asked us and our supplier to go into escrow and modify ...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentFeb 13, 2023
Washington
Hello, I'm newer to owning a business. I have missed my mechanics lein notice deadline. The customer hasn't paid me fully for the job. What are my options
in WA state?
...Read More
Anonymous Contractor
1 answerAdd commentFeb 11, 2023
Washington
I didn’t receive my money from owner of the property...Read More
Yahor Hudzel
2 answersAdd commentJan 21, 2023
Washington
I am a subcontractor I haven’t got paid general contractor has been leading me on changing the date and haven’t got paid over 2 months...Read More
Rafik Iskandaryan
1 answerAdd commentJan 30, 2023
WashingtonMechanics Lien
If we are being hired by the general contractor on behalf of the property/homeowner - do we have to mail the Notice to Owner directly to the property owner
or are we covered if it just gets mailed to the general contractor since that homeowner has essentially given the GC to hire work on their behalf?
...Read More
Anonymous Contractor
1 answerAdd commentJan 26, 2023
WashingtonMechanics LienPreliminary Notice
The agreement was that we get 3 payments of 22000 we got the 1st payment of 22000 and I paid for the machinery and the middle payment of 22000 I only
got 10 of And Mr. Frank wouldn't pay me the rest of it right there is a breach of contract I couldn't finish the job due to the fact of the payment I ...Read More
...Read More
Thad Rach
1 answerAdd commentDec 6, 2022
Washington
A building owner is asking us to release our lien so that he can refinance the building. We will be working there for the next month or so, so we have plenty of
time to re-lien. My question is that if I release the lien, will I be giving up future lien rights for the same money?
...Read More
Grace Finch
1 answerAdd commentJan 17, 2023
WashingtonLien on Funds
I have a question about conditional waivers. A lot of general contractors don't pay invoices within 30 days and at the time of submitting a new invoice (which
requires the inclusion of a new conditional/unconditional lien waiver), more than the current month's billing is still outstanding. If this is the case, ...Read More
...Read More
Anonymous Contractor
1 answerAdd commentJan 17, 2023
WashingtonLien Waivers
We installed flooring in a customer home. After the installation he questioned the amount of materials. He won’t agree to a meeting to discuss the project
and quanities . He won’t pay the balance.
...Read More
Anonymous Contractor
1 answerAdd commentJan 12, 2023
Washington
The customer only wants to pay for the invoice amount....Read More
Valarie Eckloff
Waiting for answerAdd commentDec 5, 2022
Washington
We filed lien. The lein was submitted to a company, with what we thought was plenty of time. We still had a subcontractor there under our contract for 2
more months. We are in a major lawsuit now with them owing more than 300,000 to us. Around 40,000 goes to subcontractors that haven't been...Read More
...Read More
Mindy Bates
Waiting for answerAdd commentDec 20, 2022
Washington