We are an interior design firm in Florida working on a project in Texas. The builder wants us to sign a Lien waiver in the state of Texas. Can that be done?...Read More
Anonymous Contractor
1 answerAdd commentMay 11, 2018
TexasLien Waivers
Judge left off just the suffix Jr. on judgement. What effect does this have on foreclosing on real estate owned by defendant? Defendants name with JR. was on lease and numerous other docs as part of the lawsuit for which the judgment was rendered. Thoughts...Read More
Anonymous Contractor
1 answerAdd commentMay 10, 2018
TexasLien Foreclosure
We are looking into using zLien for all of our lien waiver needs, we want to be sure we have a good understanding of what the law in Texas states....Read More
Anonymous Contractor
1 answerAdd commentApr 30, 2018
TexasLien ReleasesLien Waivers
we started a job that was customer was to receive a loan for the customer has not given us a draw so now we have pulled off can we lein for the full contract amount...Read More
Anonymous Contractor
1 answerAdd commentApr 18, 2018
TexasMechanics Lien
General contractor has not paid us in two weeks. We have been working since 03-13-18 and now for the past two weeks he has not paid us(he is supposed to pay every week) per contract. Our contract ends today 04-14-18 and we don’t know where to even start, we are scared because we owe these workers and we are left with no money. He owes us $31,570.00...Read More
Anonymous Subcontractor
1 answerAdd commentApr 14, 2018
TexasLien DeadlinesMechanics LienPreliminary Notice
My neighbor owns a construction business he started about 30 years ago. The last couple of years has been a struggle for several reasons; his wife became very ill; projects were completed but not tracked for payment so he has both old and new debt that he wants me to help collect. His office manager of many years retired and the replacements have not worked out. I have some experience in debt collection but not construction. He has not been successful in finding the right person for this job and he is convinced I am the person that can turn this around. And, I think I can certainly do more than is being done but I need to know the most efficient and law abiding process to get cash flow to his company. Since some of these debts are up to 6 months past due can I still start the collection process with the Preliminary Notice....Read More
Anonymous Contractor
1 answerAdd commentApr 12, 2018
TexasLien DeadlinesMechanics LienPreliminary NoticeRecovery Options
Can I continue to send an Intent to Lien each month or do I send one and if they don’t pay I MUST send an actual lien? Is there a time frame I must do it in?...Read More
Anonymous Contractor
1 answerAdd commentApr 11, 2018
TexasLien DeadlinesMechanics LienNotice of Intent to Lien
The sub is contracted through us for a TX project. They have not issued the required 2nd and 3rd month notices. Do they have a lien claim without this? They have a supplier that is owed and has not issued their notices as well. One invoice from Nov. is on their claim, which they should have send notices on and filed their lien by March 15. They have not lien rights for this claim correct? Do they have any other recourse that could affect us or our contract with the owner? The other invoice is from January, which we are just being made aware of now by them contacting us. Still no 2nd month notice. Does the letter suffice as their notice and if so ensures they have a lien claim?...Read More
Anonymous Contractor
1 answerAdd commentApr 11, 2018
TexasMechanics LienPayment DisputesPreliminary Notice
I was hired by a GC to replace 3 HVAC systems in a burned out church. A mechanical permit was pulled by our Company and 50% of the signed proposal was paid. A city inspector conducted a preliminary inspection because the GC would not provide access to the new location of the replacement equipment stating we had to entail the cost. After 4 days the GC complied with the inspector request to provide access. At 95% completion of the project a cover-up inspection was conducted and pointed out that motorized fresh air would have to be installed for the project to pass the final. A change order was sent to the GC for the installation of the motorized fresh air dampers. The GC stated he was paying the change order and if we did not install the motorized dampers by a certain date we would be fired off the job. Two days later the GC went to the City and terminated our permit and would not let us access the building to finish the project. A final bill was sent on that date....Read More
Anonymous Contractor
1 answerAdd commentApr 10, 2018
TexasMechanics LienPayment Disputes
Should I still send out lien notices to a contractor who has already filed bankruptcy?...Read More
Anonymous Contractor
1 answerAdd commentApr 9, 2018
TexasBankruptcyPreliminary Notice
I am a material supplier, who supplied a $3k fire valve to a fire contractor on 12/5/17. That contractor installed it in an apartment complex in Mesquite Texas. The contractor had received the invoice on 12/5/17 as well as a statement every month on the 1st and 15th since. I was getting pushed off, but now I need to follow legal action. What steps do I need to take to start this process thru ZLien? Also, is there a point in the process where I can physically go and repossess my product?...Read More
Anonymous Contractor
1 answerAdd commentApr 6, 2018
TexasMechanics LienRecovery Options
I had a house built and my builder hired someone to build the fence. We signed an agreement that I would pay the builder after closing on the home based on the estimate he provided. He wouldn't send a copy of the invoice or receipt of the job. I found out the contractor he said did the work, actually did not do the work and I have that in writing. He won't tell me who did the work or if it's under warranty but expects me to pay what's on the contract agreement we signed. If I don't pay him, can he put a mechanical lien on my home if he didn't actually do the work himself?...Read More
Anonymous Contractor
1 answerAdd commentApr 3, 2018
TexasConstruction ContractMechanics LienPayment Disputes
as a GC, do we even have to care of an owner files an Affidavit of Completion? To lien, we have to file by the 15th day of the 4th month following unpaid draw, so January unpaid, means we file lien by May 15 and so on. Fund trapping notice (retention) is to be filed following completion, so we would file after we are done providing to the site correct?...Read More
Anonymous Contractor
1 answerAdd commentApr 3, 2018
TexasMechanics LienRetainage
I am building a new house. I have a Builder that holds the Mechanic's Lien rights. I would like to contract directly with each tradesman instead of having those contracts go through the Builder. Is that allowed? I plan to secure Lien Waivers from each tradesman. In this case, I'd be listed for both "the person with whom you contracted" and as the "owner". Is it valid to have my name in two locations on the statutory lien waiver form (Texas Property Code Chapter 53)?...Read More
Anonymous Contractor
1 answerAdd commentApr 3, 2018
TexasConstruction ContractMechanics Lien
We are a equipment rental company. If we contracted directly with the property owner and they have stopped paying us and no notices have been sent. Do we have lien rights regardless? The project was entered in Zlien and the equipment is still on their site....Read More
Anonymous Contractor
1 answerAdd commentMar 29, 2018
TexasMechanics LienPreliminary Notice