When does the 20 days begin for the required time between sending and NOI and filing a lien?

WyomingLien DeadlinesNotice of Intent to Lien
Anonymous General Contractor

I am about to send a NOI to one of our customer and I see that I have to send that 20 days before filing a lien. When does that 20 days begin? Is it when it is sent or received?

1 reply

Levelset Admin at Levelset
| 1,007 reviews
Feb 27, 2020
Wymoming's Notice of Intent to Lien requirement stems from § 29-2-107 of the state's mechanics lien statute. And, according to that section, "The notice shall be sent no later than twenty (20) days prior to filing a lien statement." So, based on the language of that section, the 20-day clock for a Wyoming Notice of Intent will run from the date the notice is sent - not from when it's received. However - if there's time before the lien deadline, it might be worthwhile to play things safe and wait a bit longer to proceed with the lien claim. After all, a Notice of Intent is a powerful recovery tool all by itself.
The information presented here is not legal advice and should not be construed as such. Rather, this content is provided for informational purposes. Do not
act on this information as if it is advice. Further, this post does not create any attorney-client relationship. If you do need legal advice, seek the helSee More...