hello, I had a conversation yesterday with Levelset but I messed up, the project is NC not SC.
1 reply
Apr 17, 2020
The deadline to file a North Carolina mechanics lien is 120 days after last furnishing labor or materials to the project. For more info on North Carolina lien claims and deadline considerations: North Carolina Mechanics Lien Guide and FAQs.
Additionally, if you've got a question about an order in the Levelset system, or if you need to talk to a Levelset employee, feel free to contact the Levelset Support team or your account manager!