Lien for verbal change orders.

GeorgiaBond ClaimsCash FlowChange OrdersCollectionsCredit ManagementPayment Bond
Anonymous Subcontractor

I am a sub-contractor working for a General contractor on a puplic project. They have not paid us for several verbal change orders they gave us and supervised the work. We filed a lien against them and notified the University of Ga. Can I get paid.

2 replies

Levelset Admin at Levelset
| 80 reviews
Dec 24, 2020

In Georgia, if contractors and suppliers don't get paid on a construction project, they can file a lien to secure payment. There are few important dates subcontractors must keep in mind if filing a mechanics lien to secure payment owed. Once the lien was filed, in Georgia, all lien claimants must initiate enforcement of the lien within 365 days from the date on which the lien was filed. 

If there was an improvement made to a property and a claimant was not paid for their work, likely there are mechanics lien rights available. 

1 person found this helpful
Helpful
Attorney and Owner at The Storrs Law Firm
| 99 reviews
Dec 29, 2020

The good news is that there should be a payment bond protecting providers of labor and materials. Your next step should involve have counsel review the matter. If appropriate, an attorney can send a strongly worded demand for you to your customer, and work to ensure your payment bond rights are protected. Please contact me if I can be of further guidance or assistance.

This forum is not a secure form of communication. Use of this forum to contact Richard J. Storrs or the Storrs Law Firm does not create an attorney-client
relationship. No attorney client relationship exists with Richard J. Storrs or the Storrs Law Firm in the absence of a signed engagement letter. By uSee More...
See More...
1 person found this helpful
Helpful