GC is not responsive about our payments at a little rock job since November no issues with our paperwork on texture we show PM-Hold. the money that is owed is $138,753.18 this does not include retention or COs, which now they are trying to back charge us on the Co's adding non-contract items, and with things that needed to be fixed, we never got a 48h notice.