I'm a subcontractor that finished a job and did extra work as the general contractor asked us to do. It was mostly trade damage, they never approved our pay after we already did the extra work for them. They haven't really refused to pay for the extra work, their Project Administrator called our Change Order price ridiculous. Our employees took pictures and have proof of the extra work we did. They are refusing to pay for change order work after the fact.