About Stuart Zisholtz
Stuart Zisholtz is a construction attorney who works in New York, New York. Since being admitted to the New York State Bar, Stuart has litigated hundreds of
cases and has successfully argued, on multiple occasions, in the New York Court of Appeals.

Stuart is a co-author, with Gerald, of "Mechanics Liens - What's it All About". He also often lectures at many associations and is regarded a top Construction
Lawyer in New York. He has also been nominated as a "Super Lawyer" since 2011. More...
More...
Stuart Zisholtz's Recent Answers
Aug 10, 2021
Aug 10, 2021
From Nobutaka Ashihara
New York
Jul 27, 2021
From an Anonymous Contractor
New YorkLien Deadlines
Stuart Zisholtz
Attorney at Zisholtz & Zisholtz, LLP
The lien expired 1 year after it is filed. It cannot be revived once its dead. If you did work within the last 8 months, you can refile a lien.See More...
Jul 26, 2021
From an Anonymous Contractor
New YorkMechanics Lien
Stuart Zisholtz
Attorney at Zisholtz & Zisholtz, LLP
NY County does not have their liens online. The only way to check would be to go to the Clerk's office.See More...
Jul 19, 2021
From John Ackerson
New YorkLien Deadlines
Stuart Zisholtz
Attorney at Zisholtz & Zisholtz, LLP
On commercial property, you can renew the lien the first time without a court order. You can also extend it 2 more times but would need a Court Order. On
residential properties, you need a Court Order and can only renew the lien twice.
See More...