General Contractor
Review the 294 Dimas Bros. Construction projects and payment history over the years. Know more about who you work with, how they pay, and avoid any potential issues on the job.
project
last
12 months
state
average
national
industrial average
Protected Projects
0%
34%
37%
Unprotected Projects
83%
53%
56%
Reported Slow Payment
16%
7%
2%
Projects With Liens
1%
6%
5%
Commercial Construction Project at
1463 TO TAMARRON PKWAY, Katy, TX 77449
State / County Construction Project at
CR 53 AND CR 48, Manvel, TX 77578
State / County Construction Project at
2903 County Rd 81, Rosharon, TX 77583
State / County Construction Project at
3105 B F TERRY BOULEVARD, Rosenberg, TX 77471
State / County Construction Project at
CALDWELL RANCH BLVD, Rosharon, TX 77583
State / County Construction Project at
FOSTER CREEK DR, Richmond, TX 77406
State / County Construction Project at
langley bend ln & walton reach dr, Pattison, TX 77423
State / County Construction Project at
25402 Terrain Park Dr, Spring, TX 77373
State / County Construction Project at
jordan rd & igloo rd, Brookshire, TX 77423
State / County Construction Project at
14019 Broadway St, Pearland, TX 77584
State / County Construction Project at
JORDAN RANCH AND TAMARRON PKWY, Fulshear, TX 77423
State / County Construction Project at
COUNTY RD 383 COUNTY RD 57, Rosharon, TX 77583
State / County Construction Project at
3303 ANGELS REST CT, Spring, TX 77373
State / County Construction Project at
1101 Foster Xing, Richmond, TX 77406
State / County Construction Project at
JORDAN RD AND TAMMARRON PKWY, Fulshear, TX 77494
State / County Construction Project at
via aurelia dr & via lucera dr, Roman Forest, TX 77357
State / County Construction Project at
FULSHEAR SCHOOL RD, Fulshear, TX 77441
State / County Construction Project at
tamarron pt & igloo rd katy tx, Fulshear, TX 77441
State / County Construction Project at
tamarron pt & tamarron park dr, Fulshear, TX 77441
State / County Construction Project at
20433 Gene Campbell Rd, New Caney, TX 77357
State / County Construction Project at
2829 N MAIN ST, Stafford, TX 77477
State / County Construction Project at
END OF WINDWOOD FOREST DR, Roman Forest, TX 77357
Residential Construction Project at
6938 WATER GLEN LN, Manvel, TX 77578
State / County Construction Project at
jordan rd tammarron pkwy, Fulshear, TX 77441
State / County Construction Project at
1615 county road 57, Rosharon, TX 77583
Send an Invoice Reminder. Other contractors send an invoice reminder 15 and 25 days after sending an invoice.
Send a Notice of Intent to Lien to push for payment and avoid a mechanics lien. A notice of intent to lien results in payment on more than 95% of projects.
82% of projects in the last 12 months had no reported payment issues by other contractors.
Last 12 months - 82%
According to available information, 80% of projects in 2023 had no reported payment incidents.
2024 - 71%
2023 - 80%
2022 - 81%
2021 - 94%
Typical retainage not yet submitted for Dimas Bros. Construction.
Others typically said they were paid on invoice from Dimas Bros. Construction. See what were common payment terms.
100% Paid on invoice
Dimas Bros. Construction typically pays in 15 - 30 days. This is self-reported by other contractors at the end of projects.
100% 15 - 30 days
They do business the way it should be. Great work.