Menu
A map for the project located in Dallas, Texas.
Commercial Construction Project at

5703 S Lancaster Rd

Dallas, TX 75241

  • Last known event: 03/15/2024
  • First known event: 02/15/2022
LevelsetProjectsTexasDallas5703 S Lancaster Rd

Property Details


PROJECT TYPE

Commercial

PROPERTY OWNER

City of Dallas (TX)

CITY

Dallas

Key Facts

The project located at 5703 S Lancaster Rd, Dallas, Texas 75241 has had 13 companies do work over the last 3 years.

Lien History

There has been 2 liens at this address with a reported total value of $322,238.12.

Project History


On this project at 5703 S Lancaster Rd, Dallas, TX 75241 there have been 0 permits filed, 0 preliminary notices exchanged, 1 lien waiver exchanged between companies and 2 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.

Overview

0

PERMITS FILED

0

PRELIMINARY NOTICES

1

LIEN WAIVERS

2

LIEN HISTORY

Payment Timeline

03/15/2024

Slow Payment Reported

Slow Payment Reported Against Dcdtx Lc Holdings, Dhfc The Ridge At Lancaster Landowner, Ldg Ridge At Lancaster Lp, National Floor Covering, Xpert Design & Construction

Over $60,000


Source: Levelset Data

02/15/2024

Slow Payment Reported

Slow Payment Reported Against Dcdtx Lc Holdings, Dhfc The Ridge At Lancaster Landowner, Ldg Ridge At Lancaster Lp, National Floor Covering, Xpert Design & Construction

Over $60,000


Source: Levelset Data

02/15/2024

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Ldg Oaks Lp, Ranger Fire Inc., Xpert Design & Construction

Over $5,000


Source: Levelset Data

01/12/2024

Slow Payment Reported

Slow Payment Reported Against Red Kings Plumbing Contractors, Xpert Design & Construction

Over $10,000


Source: Levelset Data

01/12/2024

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Journeyman Construction , Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

01/12/2024

Slow Payment Reported

Slow Payment Reported Against Journeyman Construction , Xpert Design & Construction

Less than $1,000


Source: Levelset Data

01/12/2024

Slow Payment Reported

Slow Payment Reported Against Ranger Fire Inc., Xpert Design & Construction

Over $5,000


Source: Levelset Data

12/15/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Journeyman Construction , Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

12/15/2023

Slow Payment Reported

Slow Payment Reported Against Journeyman Construction , Xpert Design & Construction

Less than $1,000


Source: Levelset Data

12/15/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Ldg Oaks Lp, Ranger Fire Inc., Xpert Design & Construction

Over $5,000


Source: Levelset Data

11/15/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, HR Mechanical, Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

11/15/2023

Slow Payment Reported

Slow Payment Reported Against Xpert Design & Construction

Less than $1,000


Source: Levelset Data

11/15/2023

Slow Payment Reported

Slow Payment Reported Against Ranger Fire Inc., Xpert Design & Construction

Over $5,000


Source: Levelset Data

11/15/2023

Slow Payment Reported

Slow Payment Reported Against Journeyman Construction , Xpert Design & Construction

Less than $1,000


Source: Levelset Data

10/13/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Ldg Oaks Lp, Ranger Fire Inc., Xpert Design & Construction

Over $5,000


Source: Levelset Data

10/13/2023

Slow Payment Reported

Slow Payment Reported Against HR Mechanical, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

10/13/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, HR Mechanical, Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

10/13/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Journeyman Construction , Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

09/15/2023

Slow Payment Reported

Slow Payment Reported Against HR Mechanical, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

09/15/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, HR Mechanical, Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

09/15/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Journeyman Construction , Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

09/15/2023

Slow Payment Reported

Slow Payment Reported Against Journeyman Construction , Xpert Design & Construction

Less than $1,000


Source: Levelset Data

09/15/2023

Slow Payment Reported

Slow Payment Reported Against Ranger Fire Inc., Xpert Design & Construction

Over $5,000


Source: Levelset Data

08/15/2023

Slow Payment Reported

Slow Payment Reported Against Journeyman Construction , Xpert Design & Construction

Less than $1,000


Source: Levelset Data

08/15/2023

Slow Payment Reported

Slow Payment Reported Against Red Kings Plumbing Contractors, Xpert Design & Construction

Over $5,000


Source: Levelset Data

08/15/2023

Slow Payment Reported

Slow Payment Reported Against HR Mechanical, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

08/15/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, HR Mechanical, Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

07/14/2023

Slow Payment Reported

Slow Payment Reported Against Cowboy Drywall, Xpert Design & Construction

Over $10,000


Source: Levelset Data

07/14/2023

Slow Payment Reported

Slow Payment Reported Against Cowboy Drywall, Dcdtx Lc Holdings, Xpert Design & Construction

Over $10,000


Source: Levelset Data

07/14/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Ldg Oaks Lp, Ranger Fire Inc., Xpert Design & Construction

Over $10,000


Source: Levelset Data

07/14/2023

Slow Payment Reported

Slow Payment Reported Against Ranger Fire Inc., Xpert Design & Construction

Over $10,000


Source: Levelset Data

07/14/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, HR Mechanical, Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

07/14/2023

Slow Payment Reported

Slow Payment Reported Against Dcdtx Lc Holdings, Red Kings Plumbing Contractors, Xpert Design & Construction

Over $1,000


Source: Levelset Data

07/14/2023

Slow Payment Reported

Slow Payment Reported Against HR Mechanical, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

07/05/2023

Mechanics Lien Filed

Lien filed by Sunstate Equipment Company

Lien filed against Cowboy Drywall, Dcdtx Lc Holdings, Xpert Design & Construction

GC listed on lien: Xpert Design & Construction

$16,648


Source: Levelset Data

06/23/2023

Lien Threatened

Lien threat sent to Dhfc The Ridge At Lancaster Landowner, Ldg Oaks Lp, Ranger Fire Inc., Xpert Design & Construction

Over $10,000


Source: Levelset Data

06/15/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Ldg Oaks Lp, Ranger Fire Inc.

Over $10,000


Source: Levelset Data

06/15/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, HR Mechanical, Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

06/15/2023

Slow Payment Reported

Slow Payment Reported Against Cowboy Drywall, Dcdtx Lc Holdings, Xpert Design & Construction

Over $10,000


Source: Levelset Data

06/15/2023

Slow Payment Reported

Slow Payment Reported Against Cowboy Drywall, Xpert Design & Construction

Over $10,000


Source: Levelset Data

06/15/2023

Slow Payment Reported

Slow Payment Reported Against Red Kings Plumbing Contractors, Xpert Design & Construction

Over $1,000


Source: Levelset Data

06/15/2023

Slow Payment Reported

Slow Payment Reported Against Dcdtx Lc Holdings, Red Kings Plumbing Contractors, Xpert Design & Construction

Over $1,000


Source: Levelset Data

06/15/2023

Slow Payment Reported

Slow Payment Reported Against HR Mechanical, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

06/15/2023

Slow Payment Reported

Slow Payment Reported Against Ranger Fire Inc.

Over $10,000


Source: Levelset Data

06/15/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Ldg Oaks Lp, Red Kings Plumbing Contractors, Xpert Design & Construction

Over $1,000


Source: Levelset Data

05/15/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Journeyman Construction , Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

05/15/2023

Slow Payment Reported

Slow Payment Reported Against Journeyman Construction , Xpert Design & Construction

Less than $1,000


Source: Levelset Data

05/15/2023

Slow Payment Reported

Slow Payment Reported Against Red Kings Plumbing Contractors, Xpert Design & Construction

Over $1,000


Source: Levelset Data

05/15/2023

Slow Payment Reported

Slow Payment Reported Against Cowboy Drywall, Xpert Design & Construction

Over $10,000


Source: Levelset Data

05/15/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, HR Mechanical, Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

05/15/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Ldg Oaks Lp, Ranger Fire Inc.

Over $60,000


Source: Levelset Data

05/15/2023

Slow Payment Reported

Slow Payment Reported Against Dcdtx Lc Holdings, Red Kings Plumbing Contractors, Xpert Design & Construction

Over $1,000


Source: Levelset Data

05/15/2023

Slow Payment Reported

Slow Payment Reported Against Ranger Fire Inc.

Over $60,000


Source: Levelset Data

05/15/2023

Slow Payment Reported

Slow Payment Reported Against HR Mechanical, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

05/15/2023

Slow Payment Reported

Slow Payment Reported Against Red Kings Plumbing Contractors, Xpert Design & Construction

Over $1,000


Source: Levelset Data

04/14/2023

Slow Payment Reported

Slow Payment Reported Against Ranger Fire Inc.

Over $60,000


Source: Levelset Data

04/14/2023

Slow Payment Reported

Slow Payment Reported Against Dcdtx Lc Holdings, Red Kings Plumbing Contractors, Xpert Design & Construction

Over $5,000


Source: Levelset Data

04/14/2023

Slow Payment Reported

Slow Payment Reported Against Red Kings Plumbing Contractors, Xpert Design & Construction

Over $5,000


Source: Levelset Data

04/14/2023

Slow Payment Reported

Slow Payment Reported Against Journeyman Construction , Xpert Design & Construction

Less than $1,000


Source: Levelset Data

04/14/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Journeyman Construction , Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

04/14/2023

Slow Payment Reported

Slow Payment Reported Against HR Mechanical, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

04/14/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, HR Mechanical, Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

04/14/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Ldg Oaks Lp, Ranger Fire Inc.

Over $60,000


Source: Levelset Data

03/15/2023

Slow Payment Reported

Slow Payment Reported Against HR Mechanical, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

03/15/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Journeyman Construction , Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

03/15/2023

Slow Payment Reported

Slow Payment Reported Against Journeyman Construction , Xpert Design & Construction

Less than $1,000


Source: Levelset Data

03/15/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, HR Mechanical, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

03/15/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Ldg Oaks Lp, Ranger Fire Inc.

Over $60,000


Source: Levelset Data

03/15/2023

Slow Payment Reported

Slow Payment Reported Against Ranger Fire Inc.

Over $60,000


Source: Levelset Data

03/15/2023

Slow Payment Reported

Slow Payment Reported Against Red Kings Plumbing Contractors, Xpert Design & Construction

Over $1,000


Source: Levelset Data

03/06/2023

Mechanics Lien Filed

Lien filed by Winston Water Cooler Supply

Lien filed against City of Dallas (TX), Dcdtx Lc Holdings, Dhfc The Ridge At Lancaster Landowner, Red Kings Plumbing Contractors, The Ridge At Lancaster Lp, Xpert Design & Construction

GC listed on lien: Xpert Design & Construction

Property Owner: City of Dallas (TX)

$305,590


Source: Levelset Data

02/15/2023

Slow Payment Reported

Slow Payment Reported Against Journeyman Construction , Xpert Design & Construction

Less than $1,000


Source: Levelset Data

02/15/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Journeyman Construction , Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

02/15/2023

Slow Payment Reported

Slow Payment Reported Against HR Mechanical, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

01/13/2023

Slow Payment Reported

Slow Payment Reported Against Ranger Fire Inc.

Over $60,000


Source: Levelset Data

01/13/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Ldg Oaks Lp, Ranger Fire Inc.

Over $60,000


Source: Levelset Data

01/13/2023

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Journeyman Construction , Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

01/13/2023

Slow Payment Reported

Slow Payment Reported Against Journeyman Construction , Xpert Design & Construction

Less than $1,000


Source: Levelset Data

01/13/2023

Slow Payment Reported

Slow Payment Reported Against HR Mechanical, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

12/15/2022

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Ldg Oaks Lp, Red Kings Plumbing Contractors, Xpert Design & Construction

Over $10,000


Source: Levelset Data

12/15/2022

Slow Payment Reported

Slow Payment Reported Against Red Kings Plumbing Contractors, Xpert Design & Construction

Over $10,000


Source: Levelset Data

12/15/2022

Slow Payment Reported

Slow Payment Reported Against Ranger Fire Inc.

Over $10,000


Source: Levelset Data

12/15/2022

Slow Payment Reported

Slow Payment Reported Against HR Mechanical, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

11/15/2022

Slow Payment Reported

Slow Payment Reported Against Red Kings Plumbing Contractors, Xpert Design & Construction

Over $10,000


Source: Levelset Data

11/15/2022

Slow Payment Reported

Slow Payment Reported Against Journeyman Construction , Xpert Design & Construction

Less than $1,000


Source: Levelset Data

11/15/2022

Slow Payment Reported

Slow Payment Reported Against HR Mechanical, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

10/14/2022

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Ldg Oaks Lp, Red Kings Plumbing Contractors, Xpert Design & Construction

Over $60,000


Source: Levelset Data

10/14/2022

Slow Payment Reported

Slow Payment Reported Against Red Kings Plumbing Contractors, Xpert Design & Construction

Over $60,000


Source: Levelset Data

09/15/2022

Slow Payment Reported

Slow Payment Reported Against Red Kings Plumbing Contractors, Xpert Design & Construction

Over $10,000


Source: Levelset Data

06/15/2022

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Journeyman Construction , Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

05/13/2022

Slow Payment Reported

Slow Payment Reported Against Journeyman Construction , Xpert Design & Construction

Less than $1,000


Source: Levelset Data

05/13/2022

Slow Payment Reported

Slow Payment Reported Against Red Kings Plumbing Contractors, Xpert Design & Construction

Over $1,000


Source: Levelset Data

04/15/2022

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Journeyman Construction , Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

04/15/2022

Slow Payment Reported

Slow Payment Reported Against Red Kings Plumbing Contractors, Xpert Design & Construction

Over $10,000


Source: Levelset Data

03/15/2022

Slow Payment Reported

Slow Payment Reported Against Journeyman Construction , Xpert Design & Construction

Less than $1,000


Source: Levelset Data

03/15/2022

Slow Payment Reported

Slow Payment Reported Against Red Kings Plumbing Contractors, Xpert Design & Construction

Over $5,000


Source: Levelset Data

03/15/2022

Slow Payment Reported

Slow Payment Reported Against Red Kings Plumbing Contractors, Xpert Design & Construction

Over $60,000


Source: Levelset Data

03/15/2022

Slow Payment Reported

Slow Payment Reported Against Dhfc The Ridge At Lancaster Landowner, Journeyman Construction , Ldg Oaks Lp, Xpert Design & Construction

Less than $1,000


Source: Levelset Data

02/15/2022

Slow Payment Reported

Slow Payment Reported Against Journeyman Construction , Xpert Design & Construction

Less than $1,000


Source: Levelset Data

Full Project Job Tree13

Companies


In this section, you can find all 13 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.

Lender

Unknown Company

Property Owner

Bonded by Unknown

General Contractor (2)

Bonded by Federal Insurance Company (a Chubb Company)
Bonded by Federal Insurance Company (a Chubb Company)

Subcontractor (8)

Subcontractor
Subcontractor
Fire Suppression Companies
Drywall Contractors

Supplier (2)

DC
Daltile Corporation
FE
Ferguson Enterprises, Inc.

Surety Companies (1)

FI
Federal Insurance Company (a Chubb Company)

Job Hierarchy


Lender

Unknown Company

Property Owner

Bonded by Unknown

General Contractor (2)

View All
Bonded by Federal Insurance Company (a Chubb Company)

Subcontractor (8)

View All

Supplier (2)

View All
DC
Daltile Corporation

Need cash to buy materials for this job?

Levelset will pay for your materials.

You pay us back up to 120 days later.

Apply Now