Menu
A map for the project located in Dallas, Texas.
Commercial Construction Project at

212 Melba St

Dallas, TX 75208

  • Last known event: 01/13/2023
  • First known event: 10/15/2021

Property Details


PROJECT TYPE

Commercial

PROPERTY OWNER

Gables Residential

CITY

Dallas

Key Facts

The project located at 212 Melba St, Dallas, Texas 75208 has had 15 companies do work over the last 4 years.

Lien History

There has been 6 liens at this address with a reported total value of $263,087.39.

Project History


On this project at 212 Melba St, Dallas, TX 75208 there have been 0 permits filed, 2 preliminary notices exchanged, 0 lien waivers exchanged between companies and 6 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.

Overview

0

PERMITS FILED

2

PRELIMINARY NOTICES

0

LIEN WAIVERS

6

LIEN HISTORY

Payment Timeline

01/13/2023

Slow Payment Reported

Slow Payment Reported Against Durkin Enterprises LLC, Mo Melba

Over $60,000


Source: Levelset Data

12/15/2022

Mechanics Lien Filed

Lien filed by Solid Foundations Concrete | Claimant directly hired by GC

Lien filed against Durkin Enterprises LLC, Mo Melba

GC listed on lien: Durkin Enterprises LLC

$205,223


Source: Levelset Data

12/15/2022

Slow Payment Reported

Slow Payment Reported Against Durkin Enterprises LLC, Mo Melba

Over $60,000


Source: Levelset Data

12/15/2022

Mechanics Lien Filed

Lien filed by Solid Foundations Concrete | Claimant directly hired by GC

Lien filed against Durkin Enterprises LLC, Mo Melba

GC listed on lien: Durkin Enterprises LLC

$8,900


Source: Levelset Data

11/15/2022

Slow Payment Reported

Slow Payment Reported Against Durkin Enterprises LLC, Mo Melba

Over $60,000


Source: Levelset Data

09/15/2022

Mechanics Lien Filed

Lien filed by Denali Services And Transportation

Lien filed against Durkin Enterprises LLC, Mo Melba, Solid Foundations Concrete

GC listed on lien: Durkin Enterprises LLC

$2,887


Source: Levelset Data

09/15/2022

Slow Payment Reported

Slow Payment Reported Against Durkin Enterprises LLC, Mo Melba

Over $60,000


Source: Levelset Data

05/02/2022

Mechanics Lien Filed

Lien filed by Post Tension Services of Texas

Lien filed against Durkin Enterprises LLC, Mo Melba

GC listed on lien: Durkin Enterprises LLC

$12,448


Source: Levelset Data

03/31/2022

Mechanics Lien Filed

Lien filed by Ufp New Waverly | Claimant directly hired by GC

Lien filed against Durkin Enterprises LLC, Mo Melba

GC listed on lien: Durkin Enterprises LLC

$30,150


Source: Levelset Data

03/15/2022

Mechanics Lien Filed

Lien filed by BURNCO Texas

Lien filed against Durkin Enterprises LLC, Mo Melba, Solid Foundations Concrete

GC listed on lien: Durkin Enterprises LLC

$3,480


Source: Levelset Data

03/11/2022

Lien Threatened

Lien threat sent to Durkin Enterprises LLC, Solid Foundations Concrete

Over $10,000


Source: Levelset Data

02/09/2022

Slow Payment Reported

Slow Payment Reported Against Durkin Enterprises LLC, Mo Melba, Solid Foundations Concrete

Over $1,000


Source: Levelset Data

01/12/2022

Slow Payment Reported

Slow Payment Reported Against Durkin Enterprises LLC, Mo Melba, Solid Foundations Concrete

Over $5,000


Source: Levelset Data

01/12/2022

Slow Payment Reported

Slow Payment Reported Against Durkin Enterprises LLC, Solid Foundations Concrete

Over $5,000


Source: Levelset Data

12/15/2021

Slow Payment Reported

Slow Payment Reported Against Durkin Enterprises LLC, Mo Melba

Over $10,000


Source: Levelset Data

12/15/2021

Slow Payment Reported

Slow Payment Reported Against Durkin Enterprises LLC, Solid Foundations Concrete

Over $5,000


Source: Levelset Data

12/15/2021

Slow Payment Reported

Slow Payment Reported Against Durkin Enterprises LLC, Mo Melba, Solid Foundations Concrete

Over $5,000


Source: Levelset Data

12/15/2021

Slow Payment Reported

Slow Payment Reported Against Durkin Enterprises LLC, Mo Melba, Solid Foundations Concrete

Over $10,000


Source: Levelset Data

12/15/2021

Slow Payment Reported

Slow Payment Reported Against Maxim Fire Systems

Over $5,000


Source: Levelset Data

11/15/2021

Slow Payment Reported

Slow Payment Reported Against Durkin Enterprises LLC

Over $5,000


Source: Levelset Data

11/15/2021

Slow Payment Reported

Slow Payment Reported Against Durkin Enterprises LLC, Mo Melba, Solid Foundations Concrete

Over $10,000


Source: Levelset Data

11/15/2021

Slow Payment Reported

Slow Payment Reported Against Durkin Enterprises LLC, Solid Foundations Concrete

Over $10,000


Source: Levelset Data

10/15/2021

Slow Payment Reported

Slow Payment Reported Against Durkin Enterprises LLC, Mo Melba, Solid Foundations Concrete

Over $10,000


Source: Levelset Data

10/15/2021

Slow Payment Reported

Slow Payment Reported Against Durkin Enterprises LLC, Solid Foundations Concrete

Over $10,000


Source: Levelset Data

Full Project Job Tree15

Companies


In this section, you can find all 15 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.

Lender

Unknown Company

Property Owner

Bonded by Unknown

General Contractor (1)

Bonded by Federal Insurance Company (a Chubb Company)

Subcontractor (10)

Subcontractor
Fire Suppression Companies
Concrete Contractors
Drilling Contractors
Subcontractor

Supplier (3)

FE
Ferguson Enterprises, Inc.
TS
TDR Systems Inc. t/a CHUTES International
BI
Barnsco, Inc. (TX)

Surety Companies (1)

FI
Federal Insurance Company (a Chubb Company)

Job Hierarchy


Lender

Unknown Company

Property Owner

Bonded by Unknown

General Contractor (1)

Bonded by Federal Insurance Company (a Chubb Company)

Subcontractor (10)

View All
Subcontractor

Supplier (3)

View All
FE
Ferguson Enterprises, Inc.

Need cash to buy materials for this job?

Levelset will pay for your materials.

You pay us back up to 120 days later.

Apply Now