When to File a Lien for Retainage ?

Texas

Texas law states that Notice of Retention Due must be sent no later than the 30th day after the earlier of: The date the claimant’s contract is completed, terminated, or abandoned; or The date the original contract is terminated or abandoned... *** but when do you actually need to file a lien for the retainage due ?? **

2 replies

Oct 3, 2022

It would be extremely helpful if a lawyer could chime in and answer this question ...

Apparently there are three other people that have the exact same question .....

If level set wishes to retain me and other people as clients they need to hire on a dedicated lawyer to answer these questions. Waiting for three or four days sometimes even longer for critical time sensitive answers is not acceptable.

0
Report Spam
Oct 6, 2022

Use the normal lien times to file notice and lien for the retainage

 

 

 

 