When is a Final and unconditional Lien Waiver to be submitted?

PennsylvaniaConstruction ContractLien Waivers
Anonymous Contractor

I am a GC on a project. The contract notes the GC is to submit the final and unconditional lien waiver in order to establish substantial completion. I would think final lien wavers would be due with the final invoice for Final completion and when I have all my subs final release of liens.

1 reply

Levelset Admin at Levelset
| 997 reviews
May 22, 2020
Generally, final unconditional lien waivers shouldn't be exchanged until it's time for final payment. And, there's risk in providing that waiver too early without a fully fleshed out "Exceptions" section present. This sounds a lot like another question that was recently asked at the Expert Center, so I wonder if this might have been double-posted. You can find further discussion on this situation here: When is a final unconditional lien waiver to be submitted?
The information presented here is not legal advice and should not be construed as such. Rather, this content is provided for informational purposes. Do not
act on this information as if it is advice. Further, this post does not create any attorney-client relationship. If you do need legal advice, seek the helSee More...
See More...