If after the construction project is completed, the subcontractor returns 30 days later to perform Punch List work. Will that extend the 90 days after last furnishing labor and material? Or will the original completion is the date to base the lien period?

1 reply

Aug 26, 2021

Punch list work has no effect on your 90-day lien deadline.